North American Iron Works, Inc. v. G. Dekimpe, Inc.
Cases that cite this one
4 later published cases cite this decision.
- C. H. Heist Ohio Corp. v. Bethlehem Steel Co. (Appellate Division of the Supreme Court of New York 1964)
- Regal Lumber Co. v. Buck (New York County Courts 1993)
- Carroll McCreary Co. v. People (N.Y. 1935)
- Maryland Casualty Co. v. Board of Water Com'rs of City of Dunkirk (2d Cir. 1933)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
After several months of vainly demanding payment due to it, respondent was justified in quitting work under its contract and in filing its mechanic’s hen. While appellant, as general contractor, had covenanted with the board of education not to permit any hen to be filed, respondent as subcontractor cannot be deprived of its statutory right to assert a hen, in the absence of an express covenant on its part not to file any hen.
Respondent was entitled to the value of the materials fabricated by it under the contract and stored in its shops for dehvery when needed.
Since the amendment by chapter 507 of the Laws of 1916,
Having elected to assert a lien with respect to the undelivered materials manufactured for this pubfic improvement, respondent now holds the same subject to the order of appellant, upon payment of this judgment, title having passed. The findings on all the material facts are well supported in the evidence.
The judgment should be affirmed, with costs.
Present — Finch, P. J., Merrell, O’Malley, Sherman and Townley, JJ.
Judgment affirmed, with costs.