City of Syracuse v. Dale Engineering Co.
Opinion of the Court
Defendant Dale Engineering Company was the successful bidder for a contract for resurfacing, with asphalt over brick, a portion of Genesee street in Syracuse. It gave the city a bond to secure its faithful performance of the contract. At the completion of the work this defendant gave the city a so-called maintenance bond as security that the pavement would remain in good repair for a period of five years. The latter bond was given to enable this defendant to draw the last fifteen per cent of the contract price which, otherwise, pursuant to the contract, would have been retained by the city for the five-year period. The city paid the full contract price, including pay for the extra work done by defendant pursuant to the order of the city’s engineer, and it is undisputed that the pavement went to pieces rather badly within a few months.
The defendant National Surety Company is the surety on both the faithful performance bond and the maintenance bond given by the Dale Engineering Company and recovery has been had by the city against both defendants on both bonds.
We have two actions here, for the reason that the contract was let for resurfacing a stretch of street along part of which were the tracks of a street car company, and some practical reason suggested the advisability of letting the job in two separate contracts. The same questions are involved in both actions.
Appellants raise the question whether, in any case, the plaintiff could recover on both bonds, and contend that plaintiff, having accepted the pavement and having paid for it, is confined to such damages as it may recover on the bond given and accepted for the purpose of securing maintenance. This question need not now be decided. At any future trial, the verdict, if any, obtained by plaintiff, and the judgment entered thereon, can be in such form as to enable any court to which the matter may come to determine easily the assessment of damages relating to each bond.
The important question in the case relates to the defense which was pleaded but which defendants were refused permission to prove at the trial. That defense was, in substance, that under the terms of the contract, plaintiff retained entire control over the building of the pavement, both as to work and materials, and that plaintiff, over the protest of defendant contractor, compelled defendant contractor to use materials destructive of the asphalt, after being given warning of what the result would be.
The contract is not printed in the record, but, from the portions quoted in the respective briefs, we learn that the resurfacing material was to be of asphalt. When the work was completed the surface was found to be so slippery as to be dangerous to traffic.
Let us turn now to some of the stipulations of the contract.
Paragraph B provides that “ it is further agreed * * * that the City Engineer shall * * * decide upon the amount, quality * * * and fitness of the several kinds of work and materials * * * and upon all questions which may arise relative to the fulfillment of the contract, * * * and his * * * decisions shall be final and conclusive,” etc.
Paragraph F provides that “it is further agreed that the said Engineer may make alterations in [various things] or material of the work * * * or any part thereof, either before or after the commencement of construction.” This paragraph further provides, in effect, that if, by reason of such changes, the work, ■under the contract, is lessened, the contractor shall have no pay for work thus dispensed with, but, if increased, he shall be paid actual reasonable cost plus fifteen per cent.
Paragraph M provides that “ The contractor agrees that he will perform such extra work as the Engineer may order in writing, but will not perform any extra work unless so ordered.”
With these provisions in the contract, and binding on defendant, the question is whether or not it should have been permitted to make the defense pleaded. That counsel for plaintiff anticipated such defense and claimed to be ready to meet it is shown by this remark in his opening to the jury: “ I know that there is going to be the question raised wdth reference to the effect of the Tarvia that was put on this pavement. Now, if that becomes an issue in this case, we will be prepared to show you that Tarvia — the Tarvia coat didn’t in any way harm this paving. * * * In any event, even if it had, the Dale Engineering Company put it on. The Dale Engineering Company guaranteed it * * * after they had put it on.” The last remark of counsel suggested
Even the court, at first, doubted the correctness of the harsh theory which it later adopted, for when the issue as to responsibility for the application of Tarvia first arose at the trial, the court said: “ Isn’t the real question in the case whether or not the City directed these parties to put it [Tarvia] on or whether the defendant and the City agreed to put it on and try and save the street? ” And a little later in the trial, when defendant’s counsel tried to get the plaintiff’s engineer, on cross-examination, to admit that he knew that Tarvia would destroy the asphalt, the court said: “ That will be part of your [defendant’s] case [defense] won’t it? ”
However, as the trial went on the court adopted the theory that the defendant contractor was compelled to respect every dictate of plaintiff’s engineer, whether it related to interpretation of the specifications, or to changes thereof, and at the same time was to be solely liable for any unfortunate results that might follow implicit obedience. A simple sense of justice would suggest that so much autocratic authority ought to go hand and hand with a little responsibility.
The irony of the situation appears more clearly in the fight of
The judgments and orders in these two cases should be reversed on the law and a new trial granted, with costs to appellants to abide the event.
All concur. Present — Sears, P. J., Taylor, Edgcomb, Thompson and Crosby, JJ.
In each case: Judgment and order reversed on the law and a new trial granted, with costs to the appellant to abide the event.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.