In re the Arbitration of Certain Differences between Lew Morris Demolition Co.
Opinion of the Court
Order, affirmed, with twenty dollars costs and disbursements. No opinion. Present — Martin, P. J., McAvoy, Untermyer, Dore and Cohn, JJ.; Martin, P. J., and Untermyer, J., dissent and vote to reverse and deny the motion; dissenting opinion by Untermyer, J.
Dissenting Opinion
The contract provides for arbitration only with respect to (1) “ the true construction or meaning of the drawings or specifications,” and (2) “ the true value of the extra work, or of the work omitted by the Sub
It seems to me quite evident that the claim is not for “ extra work ” but for extra cost of work required to be performed by the subcontractor under the contract. Such a claim is for damages caused by the contractor’s failure to perform the contract and is not included, nor could it have been intended to be included, in these restricted provisions for arbitration. (Matter of Marchant v. Mead-Morrison M. Co., 252 N. Y. 284, 299-301; Matter of Young v. Crescent Development Co., 240 id. 244.)
The order should be reversed and the motion denied.
Martin, P. J., concurs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.