Nugent v. State
Opinion of the Court
Plaintiff-appellant has recovered a judgment against the State for one of several items for which his claim
The decision states that the award is for 1227.18 cubic yards of rock excavation at $8 per cubic yard, less $1.02, the amount bid per yard, which had been paid as a part of the final estimate. The basis for the recovery is stated in the findings: “ That the State, through its agency, the Taconic State Park Commission interfered with the progress of the work by failing and omitting to provide the contractor with channel grades in due time to conform with the normal progress of the work, and by compelling the contractor to perform such requirement as a secondary operation subsequent to the usual and normal time for performing it which was contrary to good engineering practice. ’ ’ Claimant appeals from the judgment for inadequacy and from the portion thereof which dismisses other items of his claim, notice of which was filed September 6,1933. The first hearing was held on May 2, 1938. The judge who heard the claim died before the decision.
The proposal form furnished by the State contained an estimate, “ earth excavation 42,000 cubic yards, rock excavation 94,000 cubic yards, embankment 146,000 cubic yards.” It is admitted that the State finds no data sustaining the rock estimate. Claimant testified that as a result of bar tests it was his opinion that ledge rock did not exist on the original location at many points indicated on the State’s cross sections, and would not exceed 30,000 cubic yards, with earth excavation proportionately increased above the State’s estimate, and he believed that the contract was reasonably balanced between earth and rock excavation, with fills of sufficient depth to dispose of the rock, and sufficient earth for filling and covering the rock, so that borrow would not be required. In reliance thereon he bid $1.02 per cubic yard as a fair composite price for the entire excavation work, both earth and rock, together with fifteen cents per cubic yard for embankments which it was expected would be made from the earth excavated on the line of the road.
The claimant began work at the south end of the contract, working northerly, clearing the lines of the road, stripping and storing top soil and expecting to carry on the excavation and grading in a continuous manner to the northerly end. In about a month he was prepared to drill and excavate the first rock cut. He requested the engineers in charge to establish the grade for the tile underdrain so that he could drill and excavate the channel while the rock excavation within the roadway lines was being done. His request was refused. The engineers informed him that the “ grades for the roadway might be changed, that final grades had not been determined and trench
Claimant complains that in September, 1931, the chief engineer, Bradner, required that he abandon the orderly progress of the work which he had started at the southerly end of the road and do such grading as might be found necessary to construct a work road to the places where the four bridges were to be built by the Fox Company. The work road was to be built on the line of the new highway. Claimant testifies to an oral protest: “ I said, ‘ If we got to go and make a road, that will eat up a lot of the earth and we won’t be able to do any rock work, because we will have to keep on going to get this road. * * * It will do me a lot of harm.’ He [Bradner] said 1 It don’t make any difference, you go ahead,’ I said ‘ If I go ahead I am going ahead under protest. Somebody has to pay me for doing this work. * * * If I go ahead and make roads for trucks, I will have to use all of the earth up and I won’t have time to blast any rock. ’ ”
The Court of Claims found against the claimant on this item. He was sustained by Fox, the bridge-builder, who gives testimony: “ Q. Did you have a conversation with anyone there relative to this contract before you filed your bid? A. I did. Q. With whom? A. Mr. Bradner. Q. And in the conversation with Mr. Bradner was there any reference made by him, or by you, to the matter of your getting access to the site of these bridges, if you received the contract? * * * A. Yes, there was. Q. Give us the conversation. * * * A. As the road came up to bridge number two I asked how we were to get up to bridges one, three and four, and they told me the road would be put through by the man grading the road, where the bridges went. Q. You say they told you— A. Mr. Bradner, I am talking about. * * * Q. Was there any road built which you could use, a workable road, from the southerly end of the contract up to bridge one
The engineers for the State not only raise an issue of fact as to this item, but it is argued that claimant had to make this truck road in order to get his caterpillar-borne shovel to the bridge sites to do the channel excavating. This the claimant denies, saying he would only have to remove the trees and large boulders to permit the progress of the tractor. In connection with this argument of the State the witness Fox says: “ Q. And you knew Mr. Nugent had to get to the site of the proposed — the site of the bridges in order to excavate his channels? A. Yes. Q. And he did that work before you did your bridges? A. Yes. Q. And he went.over a workable road built by bim to do that work? A. I don’t know. * * * He went over to the bridge site; I wouldn’t call it a road. Q. He went over the same road that you used? A. No, sir. Q. When did he go over to the bridge site to do this work? A. Sometime before we went in there to go to work, around the end of September and the first part of October.” ■
Claimant is entitled to payment for the additional work he did in connection with the bridge contractor’s road, and to such damages as were caused him through interference with a proper plan of progress. An item of damage asserted is that the contractor, in carrying out the instructions of the engineer, used earth to grade the work road where, had he been permitted to proceed in an orderly way, rock would have been used in the depressions. The rock which could have been used increased the surplus which later was dumped into the swamp and covered with earth under the direction of the engineers.
Another claimed item is that the engineer required that the grade of the road be raised after it had been finally completed. This occurred at three places for distances varying from eleven hundred to twenty-seven hundred and fifty feet, the change varying from a few inches to two and a half feet. The court found
It is argued on behalf of the State that the claimant did not sufficiently protest the numerous changes. This is gainsaid by the evidence, of the claimant and by an entry in the diary of the engineer Bichardson in charge of the field work:
“ Mr. Nugent made a visit to the field office very much upset and made the following statements, that the work could be finished on time at an expense of $30,000.00; that the work wás now 80 per cent complete; that the engineers in charge were trying to make him go broke to get him off the job; that he would complete the job in spite of them; that he would have a licensed engineer on the job Monday, May 16th, 1932, who would make a check on the complete job. That the contractor would then go to Court and that somebody would go to jail — the person going to jail was not definitely named. Other statements were made about undesirable traits of the engineers in charge. None of these statements were complimentary and need not be remembered.”
The following testimony appears: “ Q. As a matter of fact,, Mr. Bichardson, considerable feeling had developed on this contract between the contractor and the engineers prior to this date! A. Mr. Nugent was very much aroused.” Bichardson further says that he made records for the purpose of criticizing the contractor in court. There is an une'xplained and very substantial change in the engineer’s estimate as to the rock removed from the new location. The aggregate of the original entries was reduced for some unexplained reason by many thousands of cubic yards. Upon the final payment it was agreed between the representatives of the State and the claimant that he expressly reserved the right to make and prosecute a claim against the State.
The contractor is entitled to recover the value of extra work and material upon quantum meruit as a measure of damages for breach of contract. (Gearty v. Mayor, etc., of New York,
Crapser, Hefferstah" and Schekck, JJ., concur; Bliss, J., taking no part.
Judgment so far as appealed from reversed on the law and facts, and a new trial ordered in the Court of Claims on the issues not hereinafter determined, with costs to the appellant to abide the event.
The court reverses the following findings of fact contained in the decision: Numbers 15, 19, 21, 22, 23, 25 and 26, and disapproves of conclusions of law numbers 2, 3, 4 and 6, and modifies finding 18 in the decision by substituting for the word “ therefore ” (sic) “ on account thereof; ” also findings of fact adopted by reference thereto in finding number 29 of the decision in paragraphs of the State’s requests to find numbered 12, 13, 15, 16, 17, 18, 19, 20, 28, 29, 30, 31, 32, 35, 36, 37, 38,,39, 40, 42, 43, 44, 45, 46, 48, 49, 50, 52, 53, 54, 58, 60, 61, 62, 64, 65, 66, 67, 68, 69, 71, 72, 73, 74, 75, 76, 77, 78, 79, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 96, 97, 98, 99, 100, 109, 110 and 111.
The court makes new findings of fachas set forth in claimant’s requests to find numbered 6, 19, 21, 22, 23, 26, 27, 29, 30, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 46, 47, 48, 52, 58, 59. 66, 67, 68,
Case-law data current through December 31, 2025. Source: CourtListener bulk data.