People v. Palmer
Opinion of the Court
In May, 1938, the Public Service Commission ordered the reconstruction of defendant’s railroad crossing under the State’s Brewster-Connectieut State Line -Highway No. 1455, in the town of Southeast, Putnam County. The work entailed was not performed under that order and related statutory provisions for the reason that shortly thereafter the project was placed on the Federal Aid Grade Crossing Program, 1938 Funds, as authorized by Federal statute (49 U. S. Stat. 1519-1521), under which it was completed in an undertaking by the “ State highway ” department, as was required. (42 U. S. Stat. 212-215, § 12; U. S. Code, tit. 23, § 13.) The undertaking was by contract with one Brogan as contractor. Prior to its letting the State and the defendants entered into a written agreement concerning the project, and therein the railroad company agreed: “ to participate in any costs which are not approved by the Federal authorities and paid for from Federal Funds ”; and it was provided that the participation would be ‘ ‘in accordance with existing laws affecting similar work in this State ”. To
The additional cost of construction of the detour under the change of plan and the damages caused by the delayed performance Avcre due to the fact that the original plan which both the State and the defendant had approved was unworkable. It . was that plan which the defendant had agreed with the State would form, and did form, a part of the framework in the contract which it had agreed the State was to let, and which it did let to Brogan. The eAddence is that the report of the borings, which may be said to have indicated the fault of the original plan, was made knoAvn to the defendants long prior to the time it approved of it. When subsequent developments necessitated the modification the railroad company participated in the negotiations incident thereto, at first disapproving the alteration as initially proposed by the State and later approving the modified plan which was carried out. The genesis of all the difficulties born of the fault in the original plan bore upon a subject matter of direct concern to the railroad company, viz.: the construction of a detour for the continued operation of its train service during the construction work of its new highway crossing.
It is conceded that under applicable statutes the railroad company’s agreement with the State called upon it to bear one half of the costs of the project, as aforestated; and the uncontradicted proof is that the costs in controversy were disapproved and not paid from Federal funds."'"-That in the State’s submission'of them for approval andho'ayment it did" not separately
In a commonly understood and general sense the word “ costs ”, when not used as a word of art, is synonymous with expense or detriment, and connotes loss of any kind incurred to secure a benefit. In the defendants’ agreement with the State we construe it as so employed. It was not otherwise defined. 'The proof is that the sum here sued for was, in that sense;; a part of the cost, of the project which the railroad company had agreed to hear. The State was acting for both itself and the defendants in letting the contract to Brogan. Their joint supervision, oyer the work involved in the construction of the detour was provided for in Brogan’s contract and exercised. Conscious conduct- on the part of each party contributed in producing"the'situation which resulted in all the unanticipated costs of the project which are in question and which: the. State has been obliged to pay. Had such costs or part thereof been attributable solely to the act or neglect of the State, a different situation would, of course, be presented, as it was in the case of Matter of City of Mt. Vernon v. New York, N. H & H. R. R. Co. (208 App. Div. 738, affd. 240 N. Y. 586).
In our opinion the proofs establish the cause of action sued upon and the judgment should be affirmed.
Foster, P. J., IIeffernan, Bergan and Coon, JJ., concur.
Judgment affirmed, with costs. [See post, p. 835.]
Case-law data current through December 31, 2025. Source: CourtListener bulk data.