Bartley Bros. Construction Corp. v. National Surety Corp.
Opinion of the Court
Appeal by defendants, sureties on a payment bond, from an order which denied their motion to stay proceedings in the action until arbitration shall have been had between plaintiff and their principals on the bond. Order reversed on the law and the facts, with $10 costs and disbursements, and motion granted, with $10 costs. Respondent has been directed to proceed to arbitration of a dispute with appellants’ principals which pre
Case-law data current through December 31, 2025. Source: CourtListener bulk data.