Bethlehem Steel Co. v. Turner Construction Co.
Opinion of the Court
The question presented on this appeal from a denial of plaintiff’s motion for summary judgment is the meaning of the words “ component materials ” in a contract by which plaintiff agreed to furnish, erect and paint all structural steel work in a building for defendant Mutual Life Insurance Company. While the contract was with the defendant Turner Construction Company, that company was acting for defendant Mutual and it is Mutual which will hereafter be referred to as the defendant. The controversy arises out of an escalator clause permitting an increase in the contract price if there should be increases in the prices of “ component materials, labor rates applicable to the fabrication and erection thereof and freight rates ” in effect as of the date of the contract.
Plaintiff increased the price of steel after the contract date, although the price increase was in fact announced before the contract was executed. Plaintiff has billed defendant for such increased prices as well as other increases permitted by the escalator clause. Defendant challenges the validity of the extra charge insofar as it relates to an increase in steel prices, contending that it was never intended that plaintiff could unilaterally increase its contract charge by increasing its own charge for steel. Defendant asserts that by ‘ ‘ component materials ”, an increase in the cost of which would justify an increase in the contract price, the parties meant materials enter
Defendant really offers nothing in support of its contention other than its own asserted understanding of the contract. We cannot find warrant for such an understanding in the contract and observe no triable issue.
The contract was for furnishing, erecting and painting structural steel work. The “ component materials ” of such work would be the steel, the paint and other materials used in erecting the steel. It could hardly mean the numerous raw products from ore to blast furnace which entered into the making of the steel. Furthermore, clearly, the labor rates applicable to the fabrication and erection of the component materials meant labor rates applicable to the fabrication and erection of the structural steel on the job and not labor rates along the steel production line. We conclude, perforce, that the escalator clause in its entirety related to the erection job and not to the manufacture of steel.
There is this to be said concerning defendant’s complaint about plaintiff’s unilaterally effecting an increase in price by raising its own quotations for steel. It is unlikely that plaintiff raised its price apart from a market-wide increase by all steel producers. While it was assumed that plaintiff would supply steel of its own making, that was not a requirement of the contract. The facts in respect to the increase in steel prices can be developed on an assessment of the amount owing plaintiff.
The order appealed from should be reversed and the motion for summary judgment granted and an assessment of the amount due plaintiff directed, with costs to appellant.
Concurring in Part
(dissenting in part). While Bethlehem’s interpretation of the words in question may prevail after a trial, I think the words themselves are not necessarily capable of only one meaning and that the precise meaning Bethlehem claims; and, therefore, their application and meaning so far as the steel price is concerned should be finally determined only after a plenary trial in which all the surrounding circumstances may be shown so as to reveal the real intention of the parties at the time.
But on Mutual’s own construction of the dispute as to the price escalation clause in question, the items based upon changes in labor rates, freight rates and prices of material purchased by Bethlehem from others for use in performance of the contract, are due to plaintiff. The parties should be able in the interest of avoiding unnecessary litigation reasonably to agree on what the total is of these items. But if they cannot or will not, I recommend that the order should direct an assessment as to these items and the entry of judgment in favor of plaintiff of the total amount found to be due thereon.
Special Term in its opinion erroneously and prematurely held to be excluded at any trial evidence with regard to similar price adjustment clauses in other similar contracts. On the trial such evidence may be relevant as indicating an accepted practice and understanding in the trade as to such price adjustment clauses.
Peck, P. J., Cohn, Breitel and Bastow, JJ., concur, in Per Curiam opinion; Dore, J., dissents in part, in opinion.
Order reversed, with $20 costs and disbursements to the appellant, the motion granted and an assessment of the amount due plaintiff directed.