In re the Arbitration between Livingston & Cheney-Frantex, Longford-Weavers, Inc.
In re the Arbitration between Livingston & Cheney-Frantex, Longford-Weavers, Inc.
14 A.D.2d 518; 216 N.Y.S.2d 1011; 1961 N.Y. App. Div. LEXIS 9567
Opinion of the Court
The award is invalid as to Mayar Silk Mills, Inc., not a party to. the contract or the arbitration proceeding. (Matter of Brescia Constr. Co. v. Walart Constr. Co., 264 N. Y. 260.) Moreover, the award is not mutual, final and definite (Civ. Prac. Act, ยง 1462, subd. 4) in that it fails to state the amount of damages or the basis for computation thereof. (Meyer v. Merritt, 7 A D 2d 917; Matter of Albert J. Pfeiffer, Inc. [Largman, Gray Co.], 22-2 App. Div. 62.) Concur โ Botein, P. J., Rabin, McNally, Eager and Bastow, JJ.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.