Opinion of the Court
Appeal from an order of the Supreme Court which denied a motion for a stay of arbitration. The case involves a dispute between the general contractor on a very large building construction project and a subcontractor. Between the two was a complicated, lengthy and detailed written contract. Specified therein is an item which provides that the subcontractor will be paid $30 per cubic yard for rock excavation in “ trench and footings ” and $20 per cubic yard for “ mass rock excavation”. The fact that the provision fixing $20 per cubic yard for mass rock excavation was inked with pen in an otherwise printed contract is of no consequence, because eoneededly the “inked in” provision was initialed in the
Case-law data current through September 30, 2026. Source: CourtListener bulk data.