Complete Machinery & Equipment Co. v. Gelman
Opinion of the Court
Defendant had a contract with the Department of Public Works for the dehydration of a certain area in Queens County. Defendant leased machinery for the performance of this contract from plaintiff. The leasing was by a written contract and it is this contract that is the basis of the suit.
The first cause of action is for a balance due on the rental price. The balance is made up of two items: $59 which remained unpaid on the stipulated rental, and $800 claimed to be due as additional rental under a clause of the contract. The first item is conceded. The validity of the second claim depends on the correct interpretation of the contract clause. The clause reads:
“We [plaintiff] hereby guarantee an upset price of $26,000.00 to cover the cost of rental, installation, removal and operation of a Complete Wellpoint System for a period of twelve weeks.
“ [Defendant] will pay the rental, trucking and sales tax of the Wellpoint System, a total of $6,141.22, to [plaintiff], and also carry the payroll for installation, removal and operation for a twelve week period of this Wallpoint System.
“It is further understood, that should the upset price of $26,000.00 be reduced, and that after allowing for the $6,141.22, rental, etc. and furnishing of the supervision of installation, operation and removal due to [plaintiff], the difference between the balance of the upset price, $19,858.78, for said installation, removal and operation for a twelve week period, and the final cost, will be split fifty-fifty between [plaintiff and defendant].”
The upset price of $26,000 is clearly the figure estimated for the cost of the items covered for performance of the entire job. In the event it was less, the' parties were to share the saving equally. Actually, the cost was far more, and there was no saving to share. It is true that the literal wording refers to a saving in the 12-week period, but this departure from the evident intent is easily explained. Regardless of how early the work on the contract might have been completed, defendant was obligated to pay rental for a 12-week period. And this rental was to be deducted from the upset price. In this connection, therefore, the 12 weeks is synonymous with the period of operations, and on that basis there is no sum due.
Plaintiff’s second cause of action is for additional rental, and this likewise consists of two items. The first, for $3,175.16, is for rental of additional pieces of machinery beyond those specified in the contract. This item is not disputed. The second item is for rent of the machinery covered by the contract for the period in excess of 12 weeks that the machinery was on the job. A two-week credit on this period was allowed. Trial Term allowed this item on the theory that the wording of the contract could not mean that the machinery was to be used rent free for an indefinite period and that the clause providing for free rental therefore meant for a reasonable period only. But the testimony taken to determine the true meaning proved precisely the opposite. It shows that the plaintiff, on the basis of its superior knowledge and experience in the field, assumed the risk of a longer operation, and contracted accordingly. The words “ Should the wellpoint equipment be required after the twelve week pump period, it will be left on the job at a no charge basis” express the literal and advised intent of the parties. Hence there can be no recovery for rental beyond this period.
The third cause of action, for $2,875.20, is for damage done to the machinery while on the job. Plaintiff established that there was damage in excess of reasonable wear and tear when the machinery was returned, and the amount of the damage. Defendant contends that there was no proof that such damage was the result of its negligence. Trial Term rightfully rejected defendant’s contentions. A bailor of property makes out a prima facie case upon proof that the property was returned in a damaged condition beyond the usual wear and tear envisaged by the bailment. It is then the bailee’s obligation to show that the damage arose from causes for which, for one reason or another, he is not
Other claims and the counterclaims are not the subject of appeal. The judgment should be modified on the law and the facts by reducing the same to $6,109.36, with appropriate interest, and, as so modified, affirmed, with costs to appellant.
Botein, P. J., McNally, Stevens, Steuer and Witmer, JJ., concur.
Judgment unanimously modified on the law and the facts by reducing the same to $6,109.36, with appropriate interest, and, as so modified, affirmed, with costs to appellant. Settle order on notice.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.