Erecto Corp. v. State
Opinion of the Court
Appeal by claimant from that part of a judgment entered July 20, 1967 upon a decision of the Court of Claims which dismissed the second cause of action alleged in the claim. The claimant, as assignee for the benefit of creditors of Erecto Corporation, filed its claim on December 16, 1964 wherein it alleged five causes of action arising out of a contract for the construction of traffic signs and sign structures on the Horace Harding Expressway. An award was made on two causes of action and two causes of action were withdrawn prior to trial. This appeal is from that part of the judgment of the Court of Claims which dismissed the second cause of action wherein claimant sought to recover the sum of $5,639.21 for engineering charges alleged to have been improperly deducted from the final payment due under the contract. The contract was awarded to Erecto Corporation on October 9, 1962, By its terms work was to be commenced within 10 days, and the contractor had the option of accepting the drawings prepared by the State, or submitting his own within 45 days after the awarding of the contract. The contract also permitted the use of aluminum as a substitute for steel for the construction of the sign structures. The work under the contract was to be completed by October 15,1963. Erecto Corporation chose to use aluminum and, concededly, did not commence work within 10 days or submit drawings within 45 days after the awarding of the contract. Erecto Corporation submitted drawings on April 1, 1963. These were reviewed and returned on May 8, 1963 because they did not meet the contract specifications. Drawings were again submitted on July 10, 1963 which were revised by the State and returned in August, 1963. The drawings were revised by the contractor and submitted for the third time on October 11, 1963. These drawings were-approved on October 31, 1963. On October 14, 1963 Erecto Corporation applied for an extension of the time to complete the work asserting the failure of a subcontractor to perform as the reason for the request. This application was granted, and the completion date was extended to January 31, 1964 with a provision, however, that from November 15, 1963 to the date of completion, the State would require engineering charges to be deducted from moneys due under the contract. On January 27, 1964 Erecto Corporation again requested an extension, this time on the ground of bad weather conditions. The request was granted, and the provision for deduction of engineering charges was continued on the ground that the contractor had not taken advantage of available good weather. On February 26,1964 a third request was made for an extension on the assertion of bad weather conditions. This request was granted with the same provision as to deduction of engineering charges. The work under the contract was completed on April 22, 1964 and accepted by the State on May 13, 1964. The final estimate and final agreement were issued by the State on July 31, 1964 and in October, 1964 the State tendered a final cheek which represented the moneys computed to be due to the contractor, minus the sum of $5,639.21, which the State deducted for engineering charges. This check was returned by Erecto Corporation which thereafter filed its claim on December 16, 1964. The right of the State to deduct engineering charges from the final moneys due the contractor is provided by the contract when the work embraced in the contract is not completed on or before the specified date
Case-law data current through December 31, 2025. Source: CourtListener bulk data.