Appellate Division of the Supreme Court of New York, 1968

Wever v. Lenstyle Construction Corp.

Wever v. Lenstyle Construction Corp.
Appellate Division of the Supreme Court of New York · Decided September 5, 1968
30 A.D.2d 930; 1968 N.Y. App. Div. LEXIS 3307
Wever v. Lenstyle Construction Corp.

Opinion of the Court

Motion for stay granted, without costs, upon condition that the undertaking furnished to discharge respondent’s lien remain in effect pending determination of the appeal and upon the further condition that appellant file an additional undertaking prescribed by CPLR 5519 (subd. [a], par. 2) in the sum of $2,500, as security for payment of interest and costs directed to be paid by the judgment. Gibson, P. J., Reynolds, Aulisi, Staley, Jr., and Gabrielli, JJ., concur.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.