Kremer Construction Co. v. City of Yonkers
Opinion of the Court
In a breach of contract action, defendant appeals from an order of the Supreme Court, Westchester County, dated January 11, 1972, which granted plaintiff’s renewed motion to vacate a default judgment, entered March 29, 1971, dismissing the complaint. Order affirmed, without costs. The continuation of the examination before trial of plaintiff, by its president,. Mr. Paul R. Kremer, and of defendant, shall proceed at a time and place to be fixed in a written notice of not less than 10 days, to be given by defendant, or at such time and place as may be agreed upon by the parties. If the president of plaintiff is unable, because of continued ill health, to be examined,