LaBriola v. State
Concurring in Part
(dissenting in part). Although I agree with the conclusion of the majority that claimant is entitled to an award
Herlihy, P. J., Cooke and Main, JJ., concur with Kane, J.; Greenblott, J., dissents in part and votes to remit for appropriate findings.
Judgment modified, on the law and the facts, by increasing the award to $277,680 .plus appropriate interest, and, as so modified, affirmed, without costs.
Opinion of the Court
These are cross appeals from a judgment in favor of claimant, entered January 20, 1971, upon a decision of-the Court of Claims.
- Claimant was the owner of 23.565 acres of land -on the north, side of Route 22 in the Town of North Castle, Westchester County. This property, divided into three differently zoned areas, had an 1,100-foot frontage along Route 22 and was zoned for use as a roadside business (R-B zone) along the road up to a depth of 300 feet. This first area consisted of about 7.5 acres. A middle -segment of -about 13 acres was zoned for light industrial park uses (RELIP zone) and the rear-most 3.633 acres were" residentially zoned. While claimant conducted a- nursery business -along a portion of the property fronting Route 22 in .the R-B zone, the remainder of his property was undeveloped.
On May 16, 1967, in connection with the reconstruction and relocation of Route- 22, the State appropriated, in fee, two-small parcels of land totaling .303 acre from the southeast and southwest-corners of that portion of the property which fronted Route 22, together with a temporary easement over a .small
Claimant seeks damages for the fee takings, the taking of certain buildings and improvements, the temporary easement, and consequential damages for loss of access to old Route 22. At the trial, although the experts for both parties differed in their dollar valuations, they both agreed that, as a result of the takings, the highest and best use of the former R-B zone had been reduced to RELIP usage because of the loss of frontage along old Route 22. No change in highest and best use was found in the remainder of the property.
The Court of Claims found a value of $50,000 per acre for the R-B zoned property prior to the taking, well within the range of testimony, and made an award accordingly for the fee taking. It found the value of the improvements taken to be $19,500 and the temporary easement $200. It also assigned $6,815 as the cost to cure the ramp, which had been improperly designed, but disallowed any consequential damages for the reduction in highest and best use of the former R-B zone. The court determined that the change in .highest and best use'was a result of the diversion of traffic from in front of claimant’s premises, rather than a resulting unsuitable access because df the relocation and appropriation, citing Bopp v. State of New York (19 NY 2d 368).
It is well established that a property owner has no vested right to have traffic pass in front of his property and is not entitled to damages for diversion of traffic -due to reconstruction of .a highway and impairment of remaining access to •his .property (Bopp v. State of New York, supra; Selig v. State of New York, 10 N Y 2d 34). .However, where there is not only a diversion of traffic but an elimination of normal access so as to render .the property entirely unsuitable for its former highest and best use, consequential damages can be awarded (Priestly v. State of New York, 23 N Y 2d 152). In such
The court fixed the before value of the roadside property at $50,000 per acre and made an award for the 'direct taking accordingly. After the relocation and reconstruction of Route 22, the remaining R-B zoned property suffered a reduction in its highest and best use to RBLIP -usage. Thus, there is the necessary quantum of proof in this record for the court to determine the proper award for consequential damages. Claimant’s appraiser’s testimony of after value of the RBLIP property was $17,500 per acre. Since this is higher than the value testified to by the State’s appraiser, there can be no objection to claimant’s after value. Therefore, consequential damages can be computed as f ollows:
Before Value:
7.262 acres (7.565 acres of R-B land
less .303 acre taken in fee)
at $50,000 per acre.............. $363,100
After Value:
7.262 -acres at $17,500 pe^ acre...... 127,085
Consequential Damages:............. $236,015
We find no reason to disturb the court’s findings as to other items -of damages and the judgment should be modified to include the award of consequential damages.
The judgment should be modified, on the law and the facts, by increasing the award to $277,680 plus appropriate interest, and, as so modified, affirmed, without costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.