Appellate Division of the Supreme Court of New York, 1974

Spector v. Manshul Construction Corp.

Spector v. Manshul Construction Corp.
Appellate Division of the Supreme Court of New York · Decided November 7, 1974
46 A.D.2d 745; 362 N.Y.S.2d 389; 1974 N.Y. App. Div. LEXIS 3682
Spector v. Manshul Construction Corp.

Opinion of the Court

Order, Supreme Court, New York County, entered on December 19, 1973, granting plaintiff’s motion for summary judgment, and judgment entered thereon on December 27, 1973, unanimously reversed, on the law, without costs and without disbursements, the judgment vacated, and the motion denied. Triable issues of fact exist which preclude the grant of summary judgment to the plaintiff as to its claim for extra and additional work. Plaintiff failed' to demonstrate performance of the extra work, agreement as to the price therefor or the fair and reasonable value of the extras. Furthermore, no purpose would be served by directing an assessment (see Toussoupoff v. Columbia Brgadeasting System, 19 A D 2d 865). Concur — Markewieh, J. P„ Kupferman, Steuer, Capozzoli and Yesawich, JJ.

Case-law data current through December 31, 2025. Source: CourtListener bulk data.