New-Again Construction Co. v. City of New York
Opinion of the Court
In an action to recover (1) the balance allegedly due upon a contract and (2) damages' for breach thereof, defendant appeals from an order of the Supreme Court, Kings County, dated February 25, 1974, which, upon plaintiff’s motion to dismiss the eighth defense from the answer, which motion was made-orally at the close of a trial as to the validity of that defense, (1) . dismissed the first, second, fourth, fifth, sixth and seventh defenses and (2) set the action down for an assessment of damages. Order modified, on the law, by (1) striking from the first decretal paragraph thereof the following: “First”, “Second”, “Fourth”, “Fifth”, “Sixth” and “Seventh” “Defenses” and substituting therefor: “ Eighth defense ” and (2) striking therefrom the'second decretal paragraph. As so modified, order affirmed, without costs, and case remanded to the trial court for further proceedings not inconsistent herewith. The record reveals a stipulation between the parties that the court consider, before anything else, defendant’s' eighth defense which the parties agreed was solely one of law. In that defense it was alleged- that “ plaintiff in consideration of the granting by the defendant of extensions of the contract time for the performance [sic] of the work under the contract alleged did waive "and release all claims which it might have against the defendant arising out of the said contract.” A trial relative to that defense was had and the following facts were there- adduced. On • November 13] 1967 defendant awarded plaintiff the contract for general construction work to rehabilitate the Litchfield Mansion, a famous architectural landmark building located in Prospect Park; Brooklyn. On March 1, 1968 plaintiff was notified -to begin its work by March 11, 1968 and required to eofaplete’ its work within 120 calendar days! Notwithstanding these specific time requirements, defendant did not engage an electrical contractor for some three months, thus making it impossible for plaintiff to comply with its.original 120-day completion schedule. Plaintiff, as required by the contract, submitted a written application for an extension of time - to defendant. . That request contained a provision whereby plaintiff agreed, to waive and release any and all claims it may have had against defendant in
Case-law data current through December 31, 2025. Source: CourtListener bulk data.