Allman v. Siegfried Construction Co.
Opinion of the Court
Plaintiff, employee of subcontractor Darling, recovered a judgment against the general contractor Siegfried, and subcontractor Niagara, for personal injuries sustained when he was struck by a mass of frozen earth which fell into an excavated area where he was removing sheet piling at a construction site. The jury assigned 70% of the responsibility for damages to Siegfried and 30% to Niagara, which was responsible for excavation and backfilling on the job.
Questions of fact were presented as to the negligence of these defendants and the jury’s determination of them in plaintiffs favor is supported by evidence from which it could be found that Siegfried was negligent in locating a temporary stockpile near the excavation where plaintiff was working and that Niagara was negligent in the manner in which its drivers emptied its trucks at the stockpile near plaintiffs work area.
There was also a factual issue as to the casual relation between the accident and plaintiffs permanent respiratory disability presented by the conflicting medical evidence and opinions. We will not disturb the jury’s conclusion with respect to it. However, upon the proof in the record the verdict of $400,000 was excessive, and a new trial on the issue of damages will be required unless plaintiff stipulates to reduce the verdict to the sum of $350,000, in which event the judgment will be so modified and, as modified, affirmed.
In these five related appeals Siegfried also appeals from the trial court’s dismissal of its claims for contractual indemnification against the subcontractors Niagara and Darling and for common-law indemnification against Darling; Niagara appeals from the court’s dismissal of its claim for common-law indemnification against Darling.
With respect to the dismissal of Siegfried’s claims for contractual indemnification against Darling and Niagara, we believe the disposition as to the latter subcontractor was error. The contracts between the general contractor Siegfried and each of the subcontractors who are parties to these appeals contain indemnification provisions identical to each other and not substantially different from that construed by the Court of Appeals in Margolin v New York Life Ins. Co. (32 NY2d 149). In that case the provision was found to be of sufficient dimension to require the indemnitor to indemnify the indemnitee against the latter’s own primary negligence, so long as the damages resulted from the work undertaken by the subcontractor. With that construction before us, we apply the same test there applied—viz., did the damages sustained by plaintiff arise from the work of the subcontractor sought to be charged as indemnitor?
In the case of the subcontractor Niagara, this very question was determined against it by the jury’s verdict in favor of plaintiff against Niagara. Siegfried is therefore entitled to judgment on its cross claim for contractual indemnification against the latter.
Marsh, P. J., Moule, Cardamone and Wither, JJ., concur.
In Appeal No 1 judgment, entered December 5, 1973, unanimously reversed on the facts and a new trial granted with costs to appellants to abide the event, unless the plaintiff shall, within 10 days, stipulate to reduce the verdict to the sum of $350,000, as of the date of the rendition thereof, in which event the judgment is modified accordingly and as modified affirmed, without costs.
In Appeal No 2 judgment, entered November 19, 1973, unanimously reversed, with costs and judgment granted in favor of Siegfried Construction Co., Inc. on its cross claim in accordance with opinion by Del Vecchio, J.
In Appeal No 3 judgment, entered October 10, 1973, dismissing third-party complaint, unanimously affirmed, with costs.
In Appeal No 4 judgment, entered October 4, 1973, unanimously affirmed, with costs.
In Appeal No 5 judgment, entered October 10, 1973, dismissing first cause of action in third-party complaint, unanimously affirmed, with costs.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.