Niagara Mohawk Power Corp. v. Public Service Commission
Opinion of the Court
In August of 1973 the petitioner and the New York State Electric and Gas Corporation jointly applied to the respondent for a certificate of environmental compatibility and public need with respect to a 345,000-volt electric transmission line some 65 miles long and running from a location in the Town of La Fayette, Onondaga County, to a point in
The portion of the existing right of way to be used for construction as ordered by the respondent was originally proposed by the petitioner as an alternate to its "preferred” route. While the petitioner points to many facets of the evidence which tend to establish that its preferred route was superior, nevertheless, it is apparent that in terms of rights of way, there will be less clearing of land involved by using the alternative route certified. The petitioner in its brief concedes that at portions of its preferred route it utilized existing rights of way or consolidated existing lines. It was stated in the case of Matter of County of Orange v Public Serv. Comm. of State of N. Y. (37 NY2d 762, 765) that the scope of judicial review in these proceedings is "very limited”. That the record contains substantial evidence to support the respondent’s decision is disclosed in the petitioner’s brief and in the context of this case it cannot be said that the respondent’s preference for the use of an existing right of way is so unreasonable as to be an abuse of discretion or otherwise arbitrary and capricious.
The petitioner’s attack upon the power of the respondent to order a consolidation of pre-existing facilities and in conjunction therewith an undergrounding of a portion of such preexisting facilities as a condition of the permission to proceed with construction has no substantial merit.
Subdivision 2 of section 126 of the Public Service Law expressly provides that the respondent may modify the proposed location of a new facility. Subdivision 1 of section 126 provides that the application may be granted "upon such
The petitioner contends that there has been a "taking” of its property by virtue of the consolidation and undergrounding. However, the condition imposed is clearly not a taking but simply a condition with which the petitioner must comply if it wants to proceed with its plans. In any event, in the process of rate-making, the various costs incurred in construction projects are taken into consideration.
It is to be noted that the petitioner’s contention that the viewing of the proposed and alternate locations by some or all of the respondent’s members is somehow prejudical or erroneous in this administrative proceeding is not sustained. There is no suggestion that the viewing was for anything other than the purpose of understanding the evidence before it and such action is not prohibited by article VII. It should be further noted that the petitioner did not avail itself of the opportunity to object or attend the viewing, of which it had notice.
The remaining contentions of the petitioner have been examined and are found to be without any substantial merit.
The order should be confirmed, and the petition dismissed, without costs.
Sweeney, J. P., Kane, Mahoney and Larkin, JJ., concur.