Lake Steel Erection, Inc. v. Egan
Cases that cite this one
14 later published cases cite this decision.
- Blum v. Spaha Capital Management, LLC (District Court, S.D. New York 2014)
- Lia v. Saporito (District Court, E.D. New York 2012)
- Teramo & Co. v. O'Brien-Sheipe Funeral Home, Inc. (Appellate Division of the Supreme Court of New York 2001)
- Frederes v. Ferguson (In re Frederes) (District Court, W.D. New York 1990)
- Rinaldi v. SCA La Goutte, D'Or (District Court, S.D. New York 2022)
- BAISCH, INC. v. THE PIKE COMPANY, INC. (Appellate Division of the Supreme Court of New York 2013)
- Baisch, Inc. v. Pike Co. (Appellate Division of the Supreme Court of New York 2013)
- Baisch, Inc. v. Pike Co. (Appellate Division of the Supreme Court of New York 2013)
- O'BRIEN & GERE LIMITED v. NEXTGEN CHEMICAL PROCESSES, INC. (Appellate Division of the Supreme Court of New York 2011)
- O'Brien & Gere Ltd. v. NextGen Chemical Processes, Inc. (Appellate Division of the Supreme Court of New York 2011)
- Wullschleger & Co., Inc. v. Jenny Fashions, Inc. (District Court, S.D. New York 1985)
- Young v. Whitney (Appellate Division of the Supreme Court of New York 1985)
- Spagna v. Licht (Appellate Division of the Supreme Court of New York 1982)
- Senerchia Realty Corp. v. Yonkers Community Development Agency (Appellate Division of the Supreme Court of New York 1981)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Order and judgment unanimously reversed, on the facts, with costs, and a new trial granted on the issue of damages only unless defendant shall, within 10 days of service of a copy of the order herein with notice of entry thereof, stipulate to reduce the verdict to $8,250.75 in which case the judgment is modified accordingly and, as modified, affirmed, without costs. Memorandum: This action arose out of a construction subcontract for the erection, leveling and grouting of precast concrete flooring slabs for a 10-story building. The general contractor let a subcontract to defendant Egan in 1972 for $55,000. Defendant Egan sublet the subcontract to plaintiff Lake Steel Erection, Inc., for $43,533. Before performance was completed defendant Egan relet the subcontract to Pyramid Erection Co. for $49,500. Part of the agreement between defendant Egan and Pyramid was that defendant was to receive a commission on any profit made by Pyramid on the subcontract. A commission of $300 was paid to defendant Egan who also received $2,916.25 from the general contractor for work performed by Lake Steel. This action was commenced in the City Court of Buffalo on August 10, 1973. Plaintiff Lake Steel sought $5,223.96 on a quantum meruit basis,