Quaker-Empire Construction Co. v. D. A. Collins Construction Co.
Opinion of the Court
Appeal (1) from an order of the Supreme Court at Special Term, entered June 13, 1978 in Rensselaer County, which granted a motion by plaintiff for summary judgment upon the third cause of action, and (2) from the judgment entered thereon. Plaintiff was a subcontractor to defendant, D. A. Collins Construction Co., Inc., on a road construction project which called for the construction of a portion of Interstate Route 90. Plaintiff’s subcontract covered the supply and installation of highway guard rails, fencing, bridge railings, signs and similar items for the highway. Plaintiff’s complaint contained four causes of action. The third cause of action, which is the sole subject of this appeal, was a claim against Collins for the approximate sum of $90,000 to compensate plaintiff for the escalated costs of steel products supplied by it in satisfaction of the subcontract. The defendants, in their answer, denied the substantive allegations contained in the complaint. In addition, Collins counterclaimed for damages in the sum of $70,000 resulting from plaintiff’s failure to meet certain subcontractual specifications and to perform all of the required work. Plaintiff’s claim in the third cause of action is based neither upon contract, nor upon any wrongful act or omission of Collins. The claim is made under a special statute, enacted by the New York Legislature in 1974, authorizing the payment of equitable adjustments to contractors and subcontractors who have provided petroleum and steel materials for public improvement contracts during a period of rapid price escalation in the early 1970’s (see L 1974, chs 944, 945). Pursuant to the statute, plaintiff requested an equitable adjustment allowing additional compensation to it for steel products provided on the Collins’ project. This application was submitted in the name of Collins, as general contractor, to the Department of Transportation. The application was submitted on several forms which specifically stated that it was made on behalf of plaintiff: "I understand that I am accepting the contract adjustment indicated above for the party who suffered damages due to the energy crisis and that the full amount indicated will be transmitted to Quaker-Empire Construction Co.” The applications were approved by the Department of Transportation, which allowed an adjustment in the sum of $85,740. This amount was paid to Collins on August 4, 1977. In addition, the Department also paid to Collins the further sum of $10,025 representing a similar equitable adjustment due to plaintiff in connection with another project. The latter sum was received by Collins on behalf of plaintiff on June 20, 1977. Collins never advised plaintiff that it had received the payments described above. Plaintiff first became aware of the fact in April of 1978, approximately seven months after the last payment was received by Collins. Plaintiff immediately de
Case-law data current through December 31, 2025. Source: CourtListener bulk data.