Clifton Steel Corp. v. General Electric Co.
Cases that cite this one
5 later published cases cite this decision.
- N. Bloom & Son (Antiques) Ltd. v. Skelly (District Court, S.D. New York 1987)
- Hugh O'Kane Electric Co., LLC v. MasTec North America, Inc. (Appellate Division of the Supreme Court of New York 2005)
- Hugh O'Kane Electric Co. v. MasTec North America, Inc. (Appellate Division of the Supreme Court of New York 2005)
- Fox v. Ashland Oil, Inc. (Appellate Division of the Supreme Court of New York 1987)
- Clifton Steel Corp. v. General Electric Co. (Appellate Division of the Supreme Court of New York 1981)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Appeal from an order of the Supreme Court at Special Term, entered September 8, 1980 in Albany County, which granted plaintiff’s motion to dismiss the first and second affirmative defenses contained in the answer of defendants Morin Building Products Company, Inc., and Hartford Accident and Indemnity Company, and which denied a cross motion for summary judgment made by these defendants. The defendant Morin Building Products Company, Inc. (Morin) was a subcontractor with the defendant Le Cesse Bros. Contracting, Inc., furnishing labor and materials for the construction of a building on property owned by defendant General Electric Company (G.E.) in Tonawanda, New York. Morin entered into a subcontract with plaintiff Clifton Steel Corporation (Clifton) for the installation of certain metal panels. In furtherance of the agreement, Morin forwarded to Clifton a written contract, dated August 9, 1977, specifying a consideration of $22,470 and setting forth various terms and more particularly the provisions that: (1) the contract was to be construed and enforced in accordance with the laws of Connecticut; and (2) Clifton waived its right to file a mechanic’s lien on the project. Clifton began work on the project on or about September 26, 1977 and completed it on January 13, 1978. The balance due to Clifton is conceded to be the sum of $2,502. Prior to the filing of the mechanic’s lien herein by Clifton, a dispute arose between the parties as to Clifton’s performance of another construction project for Morin. As a result of that dispute, Morin has refused to pay Clifton’s balance on the Tonawanda project. (See, also, Clifton Steel Corp. v General Elec. Co., 80 AD2d 715.) Morin defends the action seeking foreclosure of the mechanic’s lien by alleging as affirmative defenses that: (1) Clifton did not properly perform the unrelated contract; and (2) Clifton had waived its
Case-law data current through December 31, 2025. Source: CourtListener bulk data.