City of New York v. State
Opinion of the Court
OPINION OF THE COURT
In 1967, under authority of former subdivision 5 of section 340-b and former subdivision 3.3 of section 349-c of the Highway Law, claimant (City) acquired certain Staten Island property on behalf of the State by condemnation for the purpose of widening the West Shore Expressway
Under subdivision 4 of section 10 of the Court of Claims Act a claimant has six months from the accrual of a claim to file the claim. Such a claim does not accrue until the claimant possesses the legal right to be paid and to enforce its right to payment in court (City of New York v State of New York, 40 NY2d 659, 668). The State urges that such a right does not arise until appropriate governmental action is taken on the claim, here an audit by the State Comptroller. A rejection by the Attorney-General (as was done here by letter dated December 22, 1971) or by some other State governmental official was held by the Court of Appeals to be insufficient.
In City of New York v State of New York (supra) the Court of Appeals recounted the history of the relationship between the parties herein with respect to these condemnation reimbursement claims. For years the City regularly submitted separate vouchers for reimbursement of principal plus “first-year” interest, and for “post-first-year” interest, as here, and just as routinely the State ignored the post-first-year claims, neither auditing nor formally rejecting them. Finally, the City decided to take the initiative and force the issue by sending the State Comptroller a letter setting a 60-day limit beyond which the City would consider these heretofore ignored post-first-year claims constructively rejected.
In City of New York v State of New York (61 Misc 2d 517, 536) the Court of Claims rejected this procedure, rul
The Court of Appeals was dealing with timeliness, not prematurity, as appears from its opinion (40 NY2d, at p 670): “Given all of these facts, the Court of Claims’ dismissal for untimeliness, based as it was on its opinion that a failure to audit within two months after the submission of the vouchers was the equivalent of rejection, was unrealistic and cannot be permitted to stand.”
The court allowed all of the claims to stand including those as to which the 60-day notice had been sent (Claim No. 47847) and those filed with the Court of Claims “less than five months after the vouchers had been filed” (40 NY2d, at p 665), although there had been no Comptroller’s audit and no 60-day letter (Claim No. 52436). Here the City never wrote a 60-day letter to the Comptroller, but instead filed its claim with the Court of Claims more than 60 days but less than six months after submission of the unanswered and disregarded voucher. This followed the procedure ap
The realities of the situation are that the State, by its conduct, has constructively rejected this claim, notwithstanding the absence of the 60-day letter. (This is actually the last of 19 similar claims, all of which the State has treated—or, more accurately, has ignored—in the same manner.) The statute does not require such a letter. Nor did the Court of Appeals impose such a requirement (City of New York v State of New York, 40 NY2d 659, supra) in approving the City’s initiative to satisfy its claims against a stonewalling State.
Since the amount involved appears not to be in dispute, the City is entitled to summary judgment and we so direct.
The order of the Court of Claims (AmANN, J.), entered March 10, 1980, denying claimant’s motion for summary judgment and dismissing the claim without prejudice to renewal, should be reversed on the law, without costs and without disbursements, and claimant’s motion for summary judgment should be granted.
Sandler, J. P., Carro, and Bloom, JJ., concur.
Order, Court of Claims, New York County, entered on or about March 10, 1980, reversed, on the law, and the claimant’s motion for summary judgment granted, without costs and without disbursements.
[See 83 AD2d 361;—AD2d—.]
Case-law data current through December 31, 2025. Source: CourtListener bulk data.