Melniker v. Grae
Cases that cite this one
10 later published cases cite this decision.
- Tube Forgings of America, Inc. v. Mobil Oil Corp. (Appellate Division of the Supreme Court of New York 1988)
- 212 Services, LLC v. J. Anthony Enterprises Inc. (New York Supreme Court 2015)
- Ren. Reh. Systems Co. v. Faulkner (Appellate Division of the Supreme Court of New York 2011)
- In re Lowe (Appellate Division of the Supreme Court of New York 2004)
- M. Gold & Son, Inc. v. A.J. Eckert, Inc. (Appellate Division of the Supreme Court of New York 1998)
- James H. Rambo, Inc. v. Cheng K. Yu (Appellate Division of the Supreme Court of New York 1996)
- Shron v. M & G Promo Service, Ltd. (In re Anthony Sicari, Inc.) (United States Bankruptcy Court, S.D. New York 1992)
- LaPointe v. J.T.T. Contractors, Inc. (Appellate Division of the Supreme Court of New York 1989)
- Norden Electric, Inc. v. Ideal Electrical Supply Corp. (Appellate Division of the Supreme Court of New York 1989)
- Advanced Alarm Technology, Inc. v. Pavilion Associates (Appellate Division of the Supreme Court of New York 1988)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
In an action to foreclose a mechanic’s lien, the appeals are from (1) so much of a decision of the Supreme Court, Richmond County (Rubin, J.), dated May 14, 1980, as denied the appellant-intervenor’s motion insofar as it was to dismiss the complaint, without prejudice to renew after an exchange of pleadings, (2) a decision of the same court dated September 23, 1980, which denied the appellants’ motion to dismiss the complaint, and (3) stated portions of an order of the same court dated October 31, 1980, which, inter alia, denied the said motions to dismiss. Appeals from decisions dated May 14, 1980 and September 23, 1980, respectively, dismissed. No appeal lies from a decision. Order dated October 31,1980 modified, on the law, by adding provisions thereto (1) directing defendant Barbara Grae to execute an undertaking in the amount of $4,250, and (2) directing that, upon such execution, the order (if still in effect) enjoining the Chicago Title Insurance Company from paying out an escrow deposit of $5,000 is vacated and the complaint against defendant Joel Grae is dismissed. As so modified, order affirmed insofar as appealed from. Plaintiff is awarded one bill of $50 costs and disbursements. Appellants and intervenor-appellant contend that the mechanic’s lien is void since it was untimely filed. The notice of lien is valid on its face since the notice indicates that it was filed within four months after the completion of the contract (see Lien Law, § 10). Where there exists “no defect upon the face of a notice of lien, any dispute regarding the validity of the lien must await trial thereof by foreclosure” and the court cannot summarily discharge the lien (see Dember Constr. Corp. v P & R Elec. Corp., 76 AD2d 540, 546; Lien Law, § 19, subd [6]). There is a triable issue of fact as to whether plaintiff’s latest services, which were rendered within four months of the filing