Anthony L. Castiglia, Inc. v. City of Lockport
Cases that cite this one
2 later published cases cite this decision.
- CRANE-HOGAN STRUCTURAL SYSTEMS, INC v. STATE OF NEW YORK (Appellate Division of the Supreme Court of New York 2011)
- Crane-Hogan Structural System, Inc. v. State (Appellate Division of the Supreme Court of New York 2011)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Judgment unanimously modified and, as modified, affirmed, without costs, in accordance with the following memorandum: The decision for plaintiff, in its action to recover payment for materials and services provided defendant in the construction of a municipal parking garage, is supported by sufficient proof in the record. Since defendant breached the contract when it unjustifiably prevented completion, plaintiff could recover in quantum, meruit for work done (Paterno & Sons v Town of New Windsor, 43 AD2d 863). In calculating the damages, however, defendant should have been given credit for excavation payments already made, and should not have been required to pay overhead and profit on general payments retained by it under the contract, as the retainage already reflected such amounts. Therefore, judgment is modified to the sum of $283,608.51: (1) 3,600 cubic yards of garbage excavation at $1.01 per cubic yard, plus 5% overhead and 10% profit, for a total of $4,199.58; (2) 7,000 cubic yards of gravel fill, compaction and testing at $5.40 per cubic yard, plus 5% overhead and 10% profit, for a total of $43,659; (3) 883 cubic yards of rock excavation at $62.48 per yard, less credit for $4,710 already paid, for a total of $50,459.84; (4) interest on the total of the preceding three figures from
Case-law data current through December 31, 2025. Source: CourtListener bulk data.