Gottlieb Contracting, Inc. v. City of New York
Cases that cite this one
12 later published cases cite this decision.
- Tutor Perini Corp. v. State Univ. Constr. Fund (New York Supreme Court, Albany County 2025)
- Travelers Casualty & Surety Co. v. Dormitory Authority-State (District Court, S.D. New York 2010)
- NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV) (2d Cir. 2024)
- NASDI LLc v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV) (District Court, S.D. New York 2020)
- Tougher Industries, Inc. v. Dormitory Authority (Appellate Division of the Supreme Court of New York 2015)
- LoDuca Associates, Inc. v. PMS Construction Management Corp. (Appellate Division of the Supreme Court of New York 2012)
- Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority (Appellate Division of the Supreme Court of New York 2011)
- Corinno Civetta Construction Corp. v. City of New York (N.Y. 1986)
- Honeywell, Inc. v. City of New York (Appellate Division of the Supreme Court of New York 1985)
- Novak & Co. v. New York City Housing Authority (Appellate Division of the Supreme Court of New York 1985)
- Novak & Co. v. New York City Housing Authority (New York Supreme Court 1984)
- Gottlieb Contracting, Inc. v. City of New York (N.Y. 1983)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Judgment, Supreme Court, New York County (Graves, J.), entered on September 24, 1980, awarding plaintiff $35,808.24 after trial without a jury, unanimously reversed, on the law, without costs or disbursements, and the complaint dismissed. After competitive bidding plaintiff was awarded the electrical contract in connection with the rehabilitation of the Hamilton Grange Branch Library, a landmark building located on 145th Street in Manhattan. The contract price was $127,480. The contract contained exculpatory clauses which, in essence, absolved the city from any liability for damages suffered by the contractor if delayed in the performance of its work by any act or omission of the city or any other contractor having a contract with the city for the performance of work upon the site. The project was to be completed no later than July 21,1974. As a result of delays, however, plaintiff was unable to