De Foe Corp. v. City of New York
Opinion of the Court
— In an action to, inter alia, recover damages for breach of contract, defendant appeals, as limited by its brief, from so much of an order of the Supreme Court, Kings County (Rader, J.), dated October 28,1982, as (1) denied its motion for partial summary judgment dismissing the fifth and stated portions of the third causes of action asserted in the complaint and (2) granted that branch of plaintiff’s cross motion which sought to amend the third and fifth causes of actions asserted in the complaint. Order modified, on the law, by (1) deleting so much thereof as grants that branch of plaintiff’s cross motion which sought to amend the complaint and substituting therefor a provision denying the cross motion in its entirety, and (2) deleting so much thereof as denied defendant’s motion for summary judgment on the fifth and stated portions of the third causes of action and substituting therefor a provision granting said motion to the extent of dismissing items A, D and E of the third cause of action and the fifth cause of action, and denying the same in all other respects. As so modified, order affirmed, insofar as appealed from, without costs or disbursements. On or about October 2,1975, De Foe Corp., the plaintiff, entered into a contract with defendant City of New York whereby plaintiff agreed to provide all labor and material necessary for the installation of new water mains in designated areas of Kings County. On or about September 5, 1979 plaintiff commenced the instant action whereby it alleged, inter alla, that the city breached the contract. In the fifth cause of action plaintiff seeks to recover the profit lost when the city changed the material to be used in backfilling the open trenches, and to recover the cost of its overhead attributable to that portion of the contract. The contract originally called for plaintiff to supply and install clean granular sand as fill. Defendant later, in an effort to save money, demanded that excavated material be used as fill. In the third cause of action, plaintiff seeks payment for various items, labeled A, B (1), B (2), C, D, E, and F. Plaintiff claims that these items refer to additional work it was not obligated to perform under the contract and which it did perform only under protest. The claim for item B (1) has been withdrawn. The city did not move to dismiss items C and F. Thus, only the claims for items A, B (2), D and E are to be resolved on this appeal. Items A, D and E seek payment for extra repair work necessary on the installed pavement. Plaintiff contends that this extra repair work was necessary only because the city insisted that excavated material be substituted as fill for clean granular sand. Item B (2) seeks payment for certain asphalt plaintiff insists it replaced and for which the city refused to pay. On or about April 10,1981 the city moved for partial summary judgment dismissing the fifth and stated portions of the third causes of action. It maintained, inter alla, that plaintiff waived any claim it had for additional compensation for extra or disputed work by failing to comply with article 28 of the contract. That article provides, in pertinent part, that in order for a contractor to recover for disputed work or work performed under protest, the contractor must submit daily records indicating the labor involved in performing the work and the nature and quantity of any materials, plant or equipment furnished or used. Article 28 further provides that: “[fjailure to comply strictly with these requirements shall constitute a waiver of any claim for extra compensation or damages on account of the performance of such work.” It is undisputed that plaintiff never complied with this requirement by submitting labor and material records for the additional work claimed under the third cause of action. Defendant also moved for summary judgment dismissing the fifth cause of action on the ground that it failed to state a cause of action in light of article 29 of the contract. That article states, in pertinent part, that “[i]f any contract work in a unit price contract * * * is so omitted by the Commissioner,
Case-law data current through December 31, 2025. Source: CourtListener bulk data.