G. R. Lewis Construction, Inc. v. Gush
Opinion of the Court
Plaintiffs in action No. 2 planned to develop a residential subdivision to be known as Highland Hills North located in the Town of Waterford, Saratoga County. Plaintiffs hired C. T. Male Associates, P. C. (hereinafter Male) to perform engineering and surveying for the roadwork in Highland Hills North, and Male hired G. R. Lewis Construction, Inc. (hereinafter Lewis) to do the construction and installation of the roads. Male apparently prepared plans, specifications and a map of the subdivision, all of which were approved by the Town, and was to certify to plaintiffs that work was done substantially in conformance with the plans and specifications.
After Lewis substantially completed the roadwork, Male certified that the work had been performed in accordance with the specifications and recommended that Lewis be paid. Plaintiffs paid Lewis
The town moved for summary judgment dismissing Male’s third-party complaint as against it, but Special Term (Mercure, J.) denied the motion “without prejudice to renewal upon completion of examinations before trial of the parties”. Thereafter, before a different Special Term Justice (Graves, J.), the town again moved for summary judgment and, as before, the motion was denied “without prejudice to further motion at a later date”. From the order entered thereon, the town appeals.
We have recently reiterated that multiple summary judgment motions in the same action should be discouraged in the absence of newly discovered evidence or other sufficient cause (see, e.g.,
Order affirmed, with costs. Kane, J. P., Main, Mikoll, Yesawich, Jr., and Harvey, JJ., concur.
Action No. 1 apparently concerns whether this payment was sufficient for the work performed by Lewis.