Waterside Associates v. New York State Department of Environmental Conservation
Opinion of the Court
In a proceeding pursuant to CPLR article 78, inter alia, to compel the appellants New York State Department of Environmental Conservation and Commissioner Henry G. Williams (hereinafter referred to jointly as the DEC) to process the petitioner’s State Pollution Discharge Elimination System (hereinafter SPDES) permit, the appeal is from a judgment of the Supreme Court, Rich
Ordered that the judgment is reversed, on the law, without costs or disbursements, and the proceeding is dismissed.
The record reveals that in January 1982 engineers for the petitioner Butler Manor Associates (hereinafter Butler), alleged owner of a certain parcel of real property in question located in Richmond County, sent a letter to the DEC stating that development of the property was being planned and inquiring whether and to what extent the parcel consisted of wetlands. In February 1982 the engineers received a letter from the regional permit administrator which indicated that the subject property contained one freshwater wetland area and one tidal wetlands area. In December 1983 Butler allegedly entered into a contract for the sale of the parcel to the petitioner County Closing Corp. which in turn agreed to assign the contract of sale to the petitioner Waterside Associates (hereinafter Waterside). It is undisputed that in December 1984 the petitioners’ consultants invited a senior environmental analyst of the DEC to inspect the property, although the reason for the inspection is unclear. On his December inspection of the property, and on two subsequent visits made in January 1985, the analyst discovered additional areas of the parcel which he considered to be freshwater wetlands. On these occasions, he informed the petitioners’ consultant and engineer that he would designate these areas as wetlands and propose them for mapping pursuant to the Freshwater Wetlands Act.
On January 11, 1985, Waterside submitted an application to the DEC for a SPDES permit in order to construct a sewage treatment plant on the subject property. The cover letter which accompanied the application indicated, inter alia, that Waterside intended to develop 625 housing units on the parcel and expand the development to 1,000 units at a later date. However, Waterside did not submit any application for freshwater wetlands permits. By a response dated January 28, 1985, the DEC informed Waterside that the SPDES permit application would be considered incomplete pending the continued mapping of freshwater wetlands at the project site.
The petitioners then commenced the instant proceeding by service of a petition dated October 10, 1985, alleging that the 1982 letter from the DEC’s regional permit administrator, insofar as it identified only two wetlands areas on the parcel, was a negative answer under ECL 24-0703 (5) with respect to
Although the instant petition describes the relief sought as a declaratory judgment, the petitioners concede that this proceeding is actually in the nature of mandamus to compel the DEC to follow its statutory duty of refraining from all activity pursuant to the Freshwater Wetlands Act with respect to the subject property. Thus, it is clear that the four-month Statute of Limitations embodied in CPLR 217 is applicable (see generally, Lenihan v City of New York, 58 NY2d 679; Press v County of Monroe, 50 NY2d 695; Solnick v Whalen, 49 NY2d 224). In a proceeding to compel compliance with a statutory duty, the limitations period commences to run from the date upon which the officer or body refuses to honor a demand for such compliance (see, CPLR 217; Matter of De Milio v Borghard, 55 NY2d 216; Matter of Dionisio v Board of Educ., 118 AD2d 854).
The only document in the present record which could conceivably be construed as such a demand is Waterside’s SPDES permit application, which indicated that extensive development of the property was planned and sought permission to construct a sewage treatment plant. Waterside requested issuance of the permit without any regard for the provisions of the Freshwater Wetlands Act, and did not seek any construction permits in accordance with the act even though its representatives were aware that the DEC was continuing to inspect and map additional wetlands located on the property and that these activities would interfere with the application process. Hence, the application may reasonably be said to
The petitioners request that we treat the petition itself as the demand and the DEC’s answer as the requisite refusal for purposes of reviewing the limitations issue (see, e.g, Matter of Kaye v Board of Educ., 97 AD2d 794; Community Bd. No. 3 v State of New York, Off. of Mental Retardation & Developmental Disabilities, 76 AD2d 851, appeal dismissed 53 NY2d 839). However, were we to employ such reasoning, the argument would be unavailing to the petitioners because the instant proceeding would be untimely since they engaged in an unreasonably protracted delay. Indeed, the petitioners knew that the DEC was acting in alleged contravention of ECL 24-0703 (5) in December 1984 and any possible doubt concerning this issue was obviously clarified by the DEC’s response to the permit application in January 1985. Hence, if the instant petition is treated as the demand, then the ineluctable conclusion upon this record is that the petitioners engaged in an
Case-law data current through December 31, 2025. Source: CourtListener bulk data.