Golaszewski v. Cadman Plaza North, Inc.
Cases that cite this one
7 later published cases cite this decision.
- Silva v. FC Beekman Associates, LLC (Appellate Division of the Supreme Court of New York 2012)
- Mejia v. African Methodist Episcopal Allen Church (Appellate Division of the Supreme Court of New York 2000)
- Romano v. Hotel Carlyle Owners Corp. (Appellate Division of the Supreme Court of New York 1996)
- Sandi v. Chaucer Associates (Appellate Division of the Supreme Court of New York 1991)
- Public Administrator v. Trump Village Construction Corp. (Appellate Division of the Supreme Court of New York 1991)
- Evans v. Chelsea Industrial Park, Inc. (Appellate Division of the Supreme Court of New York 1990)
- Russo v. Hilman (Appellate Division of the Supreme Court of New York 1989)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
—In an action to recover damages for personal injuries, the plaintiff appeals, as limited by his brief, from so much of an order of the Supreme Court, Kings County (Williams, J.), dated April 27, 1987, as denied his motion for summary judgment, and Cadman Plaza North, Inc., and Peter J. Burgess Management Corp. appeal, as limited by their brief, from so much of the same order as denied, with leave to renew, their cross motion for summary judgment on their third-party complaint against Kano Construction Corp., doing business as Kay Construction Corp. for common-law indemnification.
Ordered that the order is affirmed insofar as appealed from, without costs or disbursements.
The plaintiff-appellant was injured when he fell from a hanging scaffold to the roof of the defendants-appellants’ building. Trial Term properly denied summary judgment to the plaintiff-appellant on the issue of liability. Although the plaintiff-appellant made out a prima facie violation of Labor Law § 240, the defendants carried their burden of showing that there existed several material issues that required a trial
The defendants-appellants sought summary judgment on their third-party complaint for common-law indemnification from third-party defendant Kano Construction Corp. only in the event the Supreme Court granted the plaintiff’s motion for summary judgment. Since plaintiff’s motion was properly denied, the Supreme Court properly did not reach the issues raised on the cross motion of the defendants-appellants and denied that cross motion with leave to renew. Mangano, J. P., Brown, Lawrence and Sullivan, JJ., concur.
Case-law data current through September 30, 2026. Source: CourtListener bulk data.