Blau Mechanical Corp. v. City of New York
Cases that cite this one
12 later published cases cite this decision.
- Law Co., Inc. v. Mohawk Const. & Supply Co. (District Court, D. Kansas 2010)
- Travelers Casualty & Surety Co. v. Dormitory Authority-State (District Court, S.D. New York 2010)
- Tutor Perini Corp. v. State Univ. Constr. Fund (New York Supreme Court, Albany County 2025)
- NASDI LLc v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV) (District Court, S.D. New York 2020)
- WDF, Inc. v. Trustees of Columbia Univ. in the City of N.Y. (Appellate Division of the Supreme Court of New York 2019)
- WDF, Inc. v. Trustees of Columbia Univ. in the City of N.Y. (Appellate Division of the Supreme Court of New York 2019)
- Bovis Lend Lease (LMB), Inc. v. Lower Manhattan Development Corp. (Appellate Division of the Supreme Court of New York 2013)
- Bovis Lend Lease (LMB), Inc. v. Lower Manhattan Development Corp. (Appellate Division of the Supreme Court of New York 2013)
- Plato General Construction Corp./EMCO Tech Construction Corp. JV, LLC v. Dormitory Authority (Appellate Division of the Supreme Court of New York 2011)
- McNamee Construction Corp. v. City of New Rochelle (Appellate Division of the Supreme Court of New York 2009)
- Eldor Contracting Corp. v. County of Nassau (Appellate Division of the Supreme Court of New York 2000)
- Manshul Construction Corp. v. Board of Education (Appellate Division of the Supreme Court of New York 1990)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
The Court of Appeals has reaffirmed the rule that a contract clause barring damages for delay in the performance of the contract is valid and "will prevent recovery of damages resulting from a broad range of reasonable and unreasonable conduct” if the conduct was contemplated by the parties when they entered into the agreement. (Corinno Civetta Constr. Corp. v City of New York, 67 NY2d 297, 305 [1986].) Such a clause will not, however, prevent recovery for damages resulting from the contractee’s intentional wrongdoing, gross negligence, or willful misconduct (Corinno Civetta Constr. Corp. v City of New York, supra; Kalisch-Jarcho, Inc. v City of New York, 58 NY2d 377 [1983]; Buckley & Co. v City of New York, 121 AD2d 933 [1st Dept 1986], lv dismissed 69 NY2d 742 [1987]). Plaintiff-respondent contracted to perform the plumbing work for the simulated tropical rain forest at the New York Zoological Park in The Bronx. Respondent was to complete the work within 730 consecutive days from the date on which defendant-appellant directed it to proceed with the work. In article 13 of the contract, respondent agreed to make "no claim for damages for delay in the performance of this contract occasioned by any act or omission to act of the City”. Respondent began work on December 8, 1977 but completed the project 709 days after the scheduled completion date. Thereafter, it instituted this lawsuit to recover damages for the delays allegedly caused by the city.
Respondent alleged that its performance was delayed by changes in the structure of the exhibit requiring modifications of the agreement which had to be approved by the Board of Estimate; a change order calling for additional excavation because subsurface conditions deviated from what was shown on appellant’s plans; and for delays allegedly caused when a local community group entered on the jobsite and threatened the workers, forcing them to leave.
The city contends that the parties foresaw the possibility that subsurface conditions at the site might materially differ
Changes in the work also were contemplated in articles 25 and 26 of the contract. The city reserved the right in article 25 to modify or change the contract, and article 26 set forth methods of payment for the extra work performed by the contractor. Thus, the possibility of changes was explicitly anticipated in the parties’ contract.
Finally, the delay caused by the intrusion of a local community group onto the work site cannot be attributed to the city, as this court held in Slattery Assocs. v City of New York (98 AD2d 686 [1st Dept 1983]). Even if it were, there is no evidence that the city’s alleged failure to provide adequate police protection was either grossly negligent or intentional and, therefore, under the holding in Corinno Civetta Constr. Corp. v City of New York (supra), damages are not recoverable for this delay. Concur—Murphy, P. J., Kupferman, Sullivan, Carro and Rosenberger, JJ.