Mekkelson v. Morris L. Cleverley Engineering
Opinion of the Court
Memorandum: Supreme Court erred by granting the motion of plaintiffs to serve an amended complaint to add Morris L. Cleverley Engineering, P. C., and CNY Consolidated Contractors, formerly known as Cleverley CM Associates, Inc., as defendants. Plaintiffs served an amended summons and complaint without leave of the court within the Statute of Limitations period, but that service was a nullity (see, Yonker v Amol Motorcycles, 161 AD2d 638; Christiansen v City of New York, 144 AD2d 328, lv denied 73 NY2d 710; Camacho v New York City Tr. Auth., 115 AD2d 691, 692; McLaughlin, Practice Commentaries, McKinney’s Cons Laws of NY, Book 7B, CPLR C1003:l, at 451). Plaintiffs did not bring the motion for leave to serve an amended complaint until after the Statute of
Case-law data current through December 31, 2025. Source: CourtListener bulk data.