Xiox Corp. v. Public Service Commission
Opinion of the Court
OPINION OF THE COURT
The Federal Public Utility Regulatory Policies Act (hereinafter PURPA; see, 16 USC §824a-3) and the Public Service Law (see, Public Service Law § 66-c) require public utility companies such as respondent Niagara Mohawk Power Corporation to purchase electricity from Federally, qualified alternate energy producing facilities (hereinafter qualifying facilities). Respondent Public Service Commission (hereinafter PSC) is charged with overseeing the contracting process and is statutorily bound, by both Federal and State law, to ensure that the amounts paid under such contracts are "just and reasonable” to the end-consumer of electricity (16 USC § 824a-3 [b] [1]; Public Service Law § 66-c [1]).
Pursuant to this authority the PSC has, at various times, established policies to aid utilities and qualifying facility developers in negotiating these mandatory power purchase contracts. Notably, the PSC generated a series of estimated "long run avoided cost”
Petitioner Xiox Corporation (hereinafter petitioner),
Petitioner applied to the PSC for a declaratory ruling that it was entitled to execution of the contracts as they were written, incorporating the 1990 LRACs. The PSC agreed that petitioner had a right to have the contracts executed, but refused to bind Niagara Mohawk to the 1990 LRACs for those contracts. Instead, it found that petitioner is only entitled to a rate based on an accurate estimate of avoided costs at the time petitioner first established a "legally enforceable obligation” (hereinafter LEO), as that term is defined by the Federal Energy Regulatory Commission regulations implementing PURPA (see, 18 CFR 292.304 [d] [2]).
Thereafter, petitioner commenced this CPLR article 78 proceeding seeking partial annulment of the PSC’s determination and enforcement of the contracts as they were initially negotiated based on the 1990 LRACs. Supreme Court confirmed the PSC’s determination and petitioner appeals.
At the outset, it should be noted that petitioner is not contesting the PSC’s decision to withdraw the 1990 LRACs, but rather argues that it acquired a vested right to those rates prior to their withdrawal and that the PSC is obliged to enforce that right by directing Niagara Mohawk to enter into the previously agreed-upon contracts which incorporate the withdrawn LRACs. We find no authority mandating the relief requested in the petition and, beyond that, we find that the PSC has adequately explained its decision not to order Niagara Mohawk to execute the contracts; accordingly, we affirm the judgment of Supreme Court.
The Federal law and implementing regulations accord a qualifying facility developer the prerogative of opting for a contract price based on a reasonable approximation of the LRACs at the time petitioner incurred the LEO (see, 18 CFR 292.304 [d] [2]). Here, the 1990 LRACs did not accurately reflect such costs; hence, the PSC rightly concluded that Federal law does not create any entitlement to the rates set
Petitioner, however, asserts that because Opinion 91-2 was an agency rule, duly promulgated in accordance with the State Administrative Procedure Act, and as such is binding on the agency, the PSC was constrained by this rule to require Niagara Mohawk to accept the use of the 1990 LRACs in petitioner’s contracts. It is undisputed that when the contracts were forwarded to Niagara Mohawk, the proposal had reached the level of certainty beyond which Opinion 91-2 suggested that replacement of the 1990 LRACs need not be incorporated. This being the case, petitioner maintains it had at that time acquired a "vested right” to utilize the 1990 LRACs, and thus the PSC’s failure to compel Niagara Mohawk to execute the contracts as written was an impermissible and unconstitutional retroactive abrogation of existing contract rights.
We are not persuaded. The portion of Opinion 91-2 relied upon by petitioner does not mandate any action on the part of the PSC, but simply sets out guidelines to assist the negotiating parties in formulating a reasonable contract in the face of changing LRACs. The opinion states that "utilities should not impose a new schedule on substantially completed negotiations merely because updated estimates were issued at an inconvenient time”, but should, in that situation, "allow developers to conclude negotiations based on an existing schedule that has been replaced” if the proposed design and contract langüage are sufficiently complete (Opinion 91-2, at 8 [emphasis supplied]). Plainly, this language imposes no obligation upon the PSC to acquiesce in or to compel the execution of a contract whose rates are not "just and economically reasonable” to the consumer or are otherwise objectionable.
Furthermore, even if the portion of Opinion 91-2 relied upon by petitioner could be considered a binding rule, the PSC has concluded that it does not apply to the situation at hand, an interpretation that is not unreasonable given the language of the opinion, and which must therefore be upheld (see, Matter of Indeck-Yerkes Energy Servs. v Public Serv. Commn.,
Inasmuch as there is no law or regulation granting petitioner the right to use the 1990 LRACs once they had been withdrawn, the PSC’s decision must be reviewed as a discretionary act. Given the PSC’s finding that the 1990 LRACs were substantially overstated and inaccurate (a determination which has not been challenged by petitioner), coupled with its overarching duty to ensure that power purchase contracts meet the statutory requirement that rates be "just and reasonable” to ratepayers, we are not disposed to conclude that the PSC’s decision to treat this situation differently from the routine LRAC replacements contemplated in Opinion 91-2, by refusing to permit the 1990 LRACs to be "grandfathered” into petitioner’s contracts, was an abuse of discretion (see, Matter of Long Is. Light. Co. v Public Serv. Commn., 137 AD2d 205, 212, lv denied 73 NY2d 703; see also, Matter of Niagara Mohawk Power Corp. v Public Serv. Commn., 138 AD2d 63, 67, lv denied 73 NY2d 702).
Weiss, P. J., Crew III, Mahoney and Harvey, JJ., concur.
Ordered that the judgment is affirmed, without costs.
. Avoided costs are those costs a utility would incur to produce the energy itself had it not purchased the energy from the qualifying facility.
. Polsky Energy Corporation, also a petitioner in this proceeding, has withdrawn its appeal.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.