Halmar Corp. v. Hudson Foundations, Inc.
Cases that cite this one
6 later published cases cite this decision.
- D. S. v. Positive Behavior Support Consulting & Psychological Resources, P.C. (Appellate Division of the Supreme Court of New York 2021)
- Trump Vil. Section 4, Inc. v. Bezvoleva (Appellate Division of the Supreme Court of New York 2018)
- Karpovich v. City of New York (Appellate Division of the Supreme Court of New York 2018)
- Lemle v. Lemle (Appellate Division of the Supreme Court of New York 2012)
- Bordan v. North Shore University Hospital (Appellate Division of the Supreme Court of New York 2000)
- Halmar Corp. v. Hudson Foundations, Inc. (Appellate Division of the Supreme Court of New York 1995)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
—In an action, inter alia, to recover damages for breach of contract, negligent misrepresentation, and fraud, the defendant Ebasco Infrastructure and Greenman-Pedersen, Inc., a joint venture, appeals, as limited by its brief, from so much of an order of the Supreme Court, Westchester County (Nastasi, J.), entered May 5, 1993, as denied its motion pursuant to CPLR 3211 (a) (7) to dismiss the sixth and seventh causes of action of the complaint insofar as they are asserted against it, and the plaintiff Halmar Corporation & Defoe Corp., a joint venture, cross-appeals from so much of the same order as denied its cross motion for discovery pursuant to CPLR 3211 (d).
Ordered that the order is modified by (1) deleting the provision thereof which denied that branch of the appellant-respondent’s motion which was to dismiss the seventh cause of action insofar as it is asserted against it and substituting therefor a provision denying that branch of the motion without prejudice to renew upon the completion of discovery, and (2) deleting the provision thereof which denied the respondent-appellant’s cross motion for discovery pursuant to CPLR 3211 (d) and substituting therefor a provision granting the cross motion; as so modified, the order is affirmed insofar as appealed and cross-appealed from, with costs to the respondent-appellant, and the matter is remitted to the Supreme Court for further proceedings consistent herewith.
The allegations in the complaint and the plaintiffs submissions in opposition to the motion of Ebasco Infrastructure and Greenman-Pedersen, Inc., a joint venture (hereinafter Ebasco), satisfy all the prerequisites to state a viable cause of action for negligent misrepresentation (see, Ossining Union Free School Dist. v Anderson LaRocca Anderson, 73 NY2d 417, 425). Although there was no contract between the plaintiff and Ebasco, the record supports the plaintiffs contention that
The factual allegations of the seventh cause of action, insofar as it is asserted against Ebasco, fail to satisfy the particularity requirements of CPLR 3016 (b). There are no allegations directly linking Ebasco to the bribery and fraudulent certification scheme perpetrated by the employees of the other subcontractors working at the job site. However, we conclude that the plaintiff has made a sufficient showing that facts essential to establish such a direct link may be uncovered during discovery proceedings. We, therefore, deny the motion to dismiss in accordance with CPLR 3211 (d) without prejudice to renew it upon the completion of discovery (see, Cerchia v V. A. Mesa, Inc., 191 AD2d 377). Rosenblatt, J. P., Ritter, Copertino and Florio, JJ., concur.