John B. Pike & Son, Inc. v. State of New York
Opinion of the Court
—Judgment unanimously modified on the law and facts and as modified affirmed with costs to claimant and matter remitted to the Court of Claims for further proceedings
On claimant’s cross appeal, we conclude that the Court of Claims erred in finding that the alternative drilling methods of claimant’s subcontractor were unauthorized under the contract and therefore noncompensable. By his "written change order”, the State engineer directed claimant to complete, by whatever means necessary, its attempts to install drains next to obstructed holes. Because experience had demonstrated the futility of not pre-drilling the holes, the subcontractor acted reasonably in determining to pre-drill the holes on the first attempt. We conclude that the subcontractor’s resort to the necessary and feasible method, sooner rather than later, was expressly or impliedly authorized by the State and thus constituted compensable extra work under the contract.
We also agree with the contention of claimant that the court erred in denying its claim for damages resulting from delays encountered in constructing the railroad overpass. The record establishes that the extraordinary and unanticipated delay was attributable to Conrail’s unreasonable refusal to accommodate claimant’s schedule. We disagree with the court’s conclusion that the State had no obligation to obtain Conrail’s cooperation. The construction contract provided that all work affecting the railroad would be "carried out under the joint supervision of the Department of Transportation and the railroad company”. Pursuant to that provision, the State
In accordance with the foregoing, we modify the judgment by finding the State liable on claimant’s first and eighth claims, and we remit the matter to the Court of Claims for a determination of damages on those claims. We have considered the remaining contentions of the parties and conclude that they are without merit. (Appeals from Judgment of Court of Claims, Margolis, Israel, J.—Breach of Contract.) Present—Denman, P. J., Balio, Fallon, Callahan and Davis, JJ.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.