Peek v. Williamsville Board of Education
Cases that cite this one
11 later published cases cite this decision.
- Carlson v. Geneva City School District (District Court, W.D. New York 2010)
- Berkowitz v. East Ramapo Central School District (District Court, S.D. New York 2013)
- Avgerinos v. Palmyra-Macedon Central School District (District Court, W.D. New York 2010)
- Brunecz v. City of Dunkirk Board of Education (Appellate Division of the Supreme Court of New York 2005)
- O'Connor v. Board of Education (Appellate Division of the Supreme Court of New York 2004)
- Buffalo Retired Teachers 91-94 Alliance v. Board of Education for City School District (Appellate Division of the Supreme Court of New York 1999)
- Peek v. Williamsville Board of Education (Appellate Division of the Supreme Court of New York 1998)
- Bidnick v. Johnson (Appellate Division of the Supreme Court of New York 1998)
- McGillicuddy v. Rush Henrietta Central School District (Henrietta Justice Court 1997)
- Seekings v. Jamestown Public School System (Appellate Division of the Supreme Court of New York 1996)
- Spoleta Construction and Development Corp. v. Board of Education of the Byron-Bergen Central School Distric (Appellate Division of the Supreme Court of New York 1995)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
—Order unanimously modified on the law and as modified affirmed without costs in accordance with the following Memorandum: Supreme
General Municipal Law § 50-i (1) (c) and Education Law § 3813 (2) require actions in tort to be commenced within one year and 90 days of the accrual of the claim. Education Law § 3813 (2-b) requires all other actions to be commenced within one year of the accrual of the claim. General Municipal Law § 50-e (5) and Education Law § 3813 (2-a) permit a court to grant leave to file a late notice of claim; however, the application must be made within the time period to commence an action under the appropriate statutory provision. A court has no authority to exceed that time limit (see, Pierson v City of New York, 56 NY2d 950, 954-956; Hall v Niagara Frontier Transp. Auth., 206 AD2d 853; Omni Group Farms v County of Cayuga, 178 AD2d 977).
Viewing the factual averments set forth in the complaint in the light most favorable to plaintiff, we conclude that the application for leave to file a late notice of claim for the causes of action sounding in tort should have been made on or before February 1994 and for the contract causes of action, on or before November 1993. The failure of plaintiff to file a timely notice of claim, or to apply within the statutory period for leave to file a late notice of claim, is jurisdictional and precludes his causes of action alleging violations of his State civil and constitutional rights (see, Hogar v Thomann, 189 AD2d 1048), his causes of action alleging a violation of his employment contract and his tenure rights that seek money damages and reinstatement (see, Spedding v Bowman, 152 AD2d 971, 972) and his defamation cause of action against defendant Banks (see, Education Law § 3813 [2]).
Plaintiffs assertion that defendant school district should be estopped from asserting a Statute of Limitations’ defense is without basis in law. The answer put plaintiff on notice that defendants raised that defense as well as plaintiff’s failure to
We modify the order on appeal, therefore, by dismissing the first and third causes of action insofar as they allege violations of plaintiffs statutory rights of tenure and civil and constitutional rights under State law, and by dismissing the second and fourth causes of action in their entirety. (Appeal from Order of Supreme Court, Erie County, Notaro, J.—Late Notice of Claim.) Present—Green, J. P., Pine, Wesley, Callahan and Davis, JJ.