In re the Arbitration between RRN Associates, Inc.
Cases that cite this one
11 later published cases cite this decision.
- Matter of Kucker Marino Winiarsky & Bittens, LLC v. Neiman (Appellate Division of the Supreme Court of New York 2024)
- Pupiales v. BLDG Mgt. Co., Inc. (Appellate Division of the Supreme Court of New York 2015)
- CITY OF OSWEGO, MTR. OF (Appellate Division of the Supreme Court of New York 2012)
- In re the Arbitration Between City of Oswego & Oswego City Firefighters Ass'n, Local 2707 (Appellate Division of the Supreme Court of New York 2012)
- Kay v. Abrams (New York Supreme Court 2008)
- Lejbik v. Allstate Indemnity Co. (Appellate Division of the Supreme Court of New York 2007)
- In re the Arbitration between North River Insurance & Morgan (Appellate Division of the Supreme Court of New York 2002)
- Bevona v. Roxanne Management (Appellate Division of the Supreme Court of New York 2001)
- Sims v. Siegelson (Appellate Division of the Supreme Court of New York 1998)
- In re the Arbitration between Wand Electric, Inc. & Clinton County Highway Department (Appellate Division of the Supreme Court of New York 1997)
- In re the Arbitration between Lubin & Schlesinger, Inc. & Scheinberg (New York Supreme Court 1996)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
—Order, Supreme Court, New York County (Richard Lowe, III, J.), entered August 28, 1995, which granted reargument and, upon reargument, vacated its prior determination confirming an arbitration award in favor of petitioner and remanded the matter to the arbitrators with respect to projects numbers 4 and 5 for "sufficient elaboration * * * in order for the court to determine whether they drew a rational conclusion that claims arising under those projects were arbitrable” and as to projects numbers 1, 2 and 3 to "provide a breakdown between the share of [respondent’s] net profits awarded to [petitioner] and any other monies due [it] on [those] projects”, unanimously reversed, on the law, with costs and disbursements, the motion for reargument denied and the previous order confirming the award reinstated.
There was no basis whatsoever upon which to grant reargument. With respect to projects numbers 4 and 5, respondent, in seeking reargument, argued that there was no agreement to arbitrate. It is undisputed, however, that respondent never sought a stay of arbitration within 20 days after service of the notice of intention to arbitrate. By failing so to move, respondent is precluded from arguing the absence of an agreement to arbitrate. (CPLR 7503 [c]; Matter of Aaacon Auto Transp. [State Farm Mut. Auto. Ins. Co.], 41 NY2d 951, cert denied 434 US 859.) Moreover, having participated in the arbitration proceeding after service upon it of a notice of intention to arbitrate, respondent waived its right to vacate the award on the ground that there was no agreement to arbitrate. (CPLR 7511 [b] [2] [ii]; see, Matter of National Cash Register Co. [Wilson], 8 NY2d 377, 382-383.) Nor, contrary to the IAS Court’s erroneous ruling, may respondent resurrect its waived claim that a valid agreement to arbitrate was never made in the guise of an argument that the arbitrators "exceeded their power.” As to projects numbers 1, 2 and 3, the award is in full settlement of all the claims and counterclaims submitted and may not be vacated for failing to set forth the arbitrators’ calculations or reasoning in reaching their award. The arbitrators are under no additional requirement to make detailed factual findings or specify the formula relied upon to reach their conclusions. (Matter of Reddick & Sons v Carthage Cent. School Dist. No. 1, 91 AD2d 1182.)
The previous order confirming the arbitration award is, in all respects, reinstated. Concur — Sullivan, J. P., Wallach, Rubin and Tom, JJ.
Case-law data current through September 30, 2026. Source: CourtListener bulk data.