Drago v. New York City Transit Authority
Cases that cite this one
14 later published cases cite this decision.
- Auclair v. Corning Incorporated (District Court, N.D. New York 2024)
- Yaucan v. Hawthorne Village, LLC (Appellate Division of the Supreme Court of New York 2017)
- Albericci v. Port Authority of New York & New Jersey (New York Supreme Court 2017)
- Ramos v. Penn Tower, LLC (Appellate Division of the Supreme Court of New York 2016)
- Riffo-Velozo v. Village of Scarsdale (Appellate Division of the Supreme Court of New York 2009)
- Lorefice v. Reckson Operating Partnership, L.P. (Appellate Division of the Supreme Court of New York 2000)
- Gniewek v. Consolidated Edison Co. (Appellate Division of the Supreme Court of New York 2000)
- Amirr v. Calcagno Construction Co. (Appellate Division of the Supreme Court of New York 1999)
- Amirr v. Calcagno Construction Co. (Appellate Division of the Supreme Court of New York 1999)
- Puckett v. County of Erie (Appellate Division of the Supreme Court of New York 1999)
- Posillico v. Laquila Construction, Inc. (Appellate Division of the Supreme Court of New York 1999)
- Snowden v. New York City Transit Authority (Appellate Division of the Supreme Court of New York 1998)
- Sacchetti v. Vasile Construction Corp. (Appellate Division of the Supreme Court of New York 1998)
- Irwin v. St. Joseph's Intercommunity Hospital (Appellate Division of the Supreme Court of New York 1997)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
In an action to recover damages for personal injuries, etc., the plaintiffs appeal from an order of the Supreme Court, Kings County (Bernstein, J.), dated May 1, 1995, which denied their motion for summary judgment.
Ordered that the order is affirmed, with costs.
The plaintiff Ronald Drago (hereinafter the injured plaintiff)
Before the injured plaintiff began work, Arnold Nelson, the assistant electrical engineer for the Transit Authority, observed the old cable hanging overhead from the column. Knowing that the old cable was live and could explode, Nelson instructed the injured plaintiff’s supervisor to properly support the cable. The injured plaintiff also noticed the dangerous condition and informed his general foreman. No action was taken to properly support the cable, and the injured plaintiff continued his work.
The plaintiffs contend that the Supreme Court should have granted their motion for summary judgment on their causes of action alleged under Labor Law §§ 200 and 241 (6). We reject this contention.
A violation of Labor Law §§ 200 or 241 (6) does not establish negligence as a matter of law (see, Long v Forest-Fehlhaber, 55 NY2d 154). Comparative negligence is a viable defense to a cause of action asserted under either Labor Law §§ 200 or 241 (6). The injured plaintiff’s knowing decision to continue with the installation of the new cable only a few feet from the live old cable creates a question of fact regarding the injured plaintiff’s potential comparative negligence (see, Lanzilotta v Lizby Assocs., 216 AD2d 229; Kelleher v First Presbyt. Church, 158 AD2d 946). Accordingly, summary judgment was properly denied. Bracken, J. P., O’Brien, Joy and Florio, JJ., concur.
Case-law data current through September 30, 2026. Source: CourtListener bulk data.