Perez v. Dime Savings Bank of New York, F.S.B.
Opinion of the Court
The court awarded damages to the respondents in the amount of $88,450 for the cost of repairs, and in the amount of $21,463.65 for lost rental income, and deducted therefrom the sum of $10,999 received by the respondents in a settlement with Allstate Insurance Company. In addition, the court directed Dime Savings to credit the respondents with all mortgage-related payments from February 10, 1991, until six months after full payment of the judgment.
Dime Savings contends, inter alia, that the court erred in finding that six months was a reasonable time within which the respondents could make repairs to the premises and in directing Dime Savings to credit the respondents with mortgage-related payments for six months following full payment of the judgment. The evidence only supports a credit from February 10, 1991, until three months after payment of the judgment, and we therefore modify the judgment accordingly.
The remaining contentions of Dime Savings are without merit (see, Nicastro v Park, 113 AD2d 129). Mangano, P. J., Sullivan, Altman and Hart, JJ., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.