Manshul Construction Corp. v. Genetech Building Systems, Inc.
Opinion of the Court
—In a proceeding pursuant to CPLR article 75 to
Ordered that the order is affirmed, with costs.
Contrary to the petitioner’s contention on appeal, the Supreme Court correctly appointed the American Arbitration Association as a successor arbitrator (see, Matter of Klines [Green], 2 AD2d 373, affd 3 NY2d 816; 5 NY Jur 2d, Arbitration and Award, § 65).
The petitioner’s remaining contentions are either without merit or not properly before this Court. Thompson, J. P., Pizzuto, Santucci and Joy, JJ., concur.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.