West Village Committee, Inc. v. Zagata
Opinion of the Court
OPINION OF THE COURT
In 1975, the Legislature enacted the State Environmental
When an administrative agency exercises its rule-making powers, it is accorded a high degree of judicial deference provided it acts within its statutory powers and the rule or regulation has a rational basis (see, Matter of Consolation Nursing Home v Commissioner of N. Y. State Dept, of Health, 85 NY2d 326, 331; Matter of Chemical Specialties Mfrs. Assn. v Jorling, 85 NY2d 382, 396; Matter of Beer Garden v New York State Liq. Auth., 79 NY2d 266, 276). Thus, to establish their causes of action, petitioners were required to show that DEC either exceeded its statutory authority or that the challenged regulations were so lacking in reason that they are essentially arbitrary (see, Ostrer v Schenck, 41 NY2d 782, 786). Our analysis shows that they failed to do so and, therefore, we conclude that Supreme Court erred in not dismissing the petition in its entirety.
Although not required by SEQRA, DEC’s regulations have recognized that lead agencies or project sponsors may engage in scoping
Petitioners claim these amendments run afoul of ECL 8-0109 (3)
Petitioners also maintain that the limitation on postscoping suggestions is arbitrary since it is often difficult for the public and involved agencies to predict with accuracy the precise nature of a project’s impact before a draft EIS has been prepared. DEC replies that the regulations do not prohibit the public from submitting additional issues after the preparation of the final written scope provided it establishes that such issues are relevant and significant (6 NYCRR 617.8 [g]). DEC points out that under the former regulations project sponsors were disinclined to participate in scoping since, without a time limitation, there was no definite end to the process resulting in delays in the preparation of the draft EIS and the inclusion of material in draft EISs that was not critical to the assessment of a project’s environmental impacts. In view of these circumstances, we cannot say that the challenged regulations lack a rational basis particularly since scoping is a voluntary procedure in which DEC is encouraging participation by project sponsors.
Petitioners fault the scoping regulations for their failure to establish a minimum time frame for public participation and to require any public notice that scoping is occurring. DEC explains that it did not establish a specific time frame for public comment since it wanted to provide lead agencies with the greatest amount of administrative flexibility possible consistent with their statutory obligation to provide reasonable and meaningful opportunity for public comment. On the issue of notice, DEC pointed out that the regulations now require that a positive declaration be published in the Environmental Notice Bulletin and state if scoping will be conducted (6 NYCRR 617.12 [a] [2] [ii]; [c]). Additional notice is provided by the circulation of the draft scope which DEC’s experience has shown is the most effective way of obtaining public comment. Moreover, these procedures for giving notice are not exclusive since a lead agency, in its discretion, may use other methods of providing notice like posting notices or media advertisements (6 NYCRR 617.12 [c] [3]). Arguably, DEC could have established other means of providing for adequate time for public comment and notice; however, we may not substitute our judgment for theirs {see, Matter of Chemical Specialties Mfrs. Assn, v Jorling, supra, at 396). Therefore, in the absence of evidentiary proof demonstrating that the means chosen by DEC are inadequate, we cannot say the regulations lack a rational basis.
The new regulations have also resulted in an expansion of the type II actions list which sets forth actions that do not require an EIS because DEC has determined that they do not have a significant effect on the environment or are otherwise precluded from environmental review (ECL 8-0113 [2] [c] [ii]; 6 NYCRR 617.5). DEC’s inclusion of the actions of the Governor (6 NYCRR 617.5 [c] [37]) has drawn opposition from petitioners who maintain that he should not be exempt from SEQRA. Reference to the statute does not resolve this issue since its definition of “agency” does not include or exclude the Governor. In interpreting the Administrative Procedure Act ([hereinafter
We believe the same reasoning applies with equal force to the constitutional office of Governor and prevents us from lightly inferring a legislative intent to impose SEQRA’s mandates upon such office. Accordingly, we find that DEC’S promulgation of 6 NYCRR 617.5 (c) (37) is not in derogation of SEQRA. In any event, petitioners’ argument appears to be more of an intellectual one than a practical one, for as one commentator has noted, virtually any conceivable act of the Governor would have to be executed by a State agency and thus fall within SEQRA (Weinberg, Practice Commentaries, McKinney’s Cons Laws of NY, Book 17½, ECL 8-0105, at 103).
Besides including the actions of the Governor in the type II list, DEC added a number of other actions
Petitioners next argue that 6 NYCRR 617.8 (a) and (f) (2) and 617.9 (b) (2) and (5) (iii) contravene ECL 8-0109 (2) and (8) in that they limit SEQRA review to only “significant” adverse environmental effects. Secondly, they contend that the effect of these regulations is to preclude lead agencies from requiring the assessments of impacts which individually are not significant but collectively are.
Our analysis does not comport with petitioners as it is well established that the purpose of an EIS is to examine the identified potentially significant environmental impacts which may result from a project, not every conceivable impact (see, Matter of Merson v McNally, 90 NY2d 742). Further, we do not read the cited regulations as restrictively as petitioners since changes in two or more elements of the environment, no one of which has a significant impact on the environment but when considered together result in a substantial adverse impact on the environment, is still one of the criteria for determining significance (see, 6 NYCRR 617.7 [c] [1] [xi]; see also, 6 NYCRR 617.7 [c] [1] [xii]).
Petitioners’ remaining contentions do not require extended discussion. There has been no improper delegation of responsibility to project sponsors for the preparation of the final EIS (see, 6 NYCRR 617.9 [b] [8]). Petitioners’ argument that DEC should have assessed the cumulative impacts the new regulations will have on New York’s waterways lacks
Cardona, P. J., Mercure, Spain and Carpinello, JJ., concur.
Ordered that the judgment is modified, on the law, without costs, by reversing so much thereof as partially granted the petition; dismiss those portions of the petition; and, as so modified, affirmed.
. For a further description of the EIS process, see Matter of Jackson v New York State Urban Dev. Corp. (67 NY2d 400, 415-416).
. The petition also contained a cause of action seeking legal fees that was dismissed and is not an issue on this appeal.
. “Scoping” means the process by which the lead agency identifies the potentially significant adverse impacts related to the proposed action that are to be addressed in the draft EIS including the content and level of detail of the analysis, the range of alternatives, the mitigation measures needed and the identification of nonrelevant issues (6 NYCRR 617.2 [af]).
. In pertinent part, ECL 8-0109 (3) provides that “ [notwithstanding any use of outside resources or work, agencies shall make their own independent judgment of the scope, contents and adequacy of an environmental impact statement”.
. These actions are commercial structures up to 4,000 square feet; school building expansions up to 10,000 square feet; one to three-family residences in approved subdivisions; accessory structures; all area variances for one to three-family residences; forest management practices on less than 10 acres of land; and the interpretation of existing codes, rules or regulations (6 NYCRR 617.5 [c] [7], [8], [9], [10], [13], [14], [31]).
Case-law data current through December 31, 2025. Source: CourtListener bulk data.