F.W. Sims, Inc. v. T. Moriarty & Son, Inc.
Opinion of the Court
—Judgment, Supreme Court, New York County (Martin Evans, J.H.O.), entered September 2, 1998, after a nonjury trial, which, to the extent appealed from, limited plaintiffs recovery of delay damages to the principal sum of $4,095, unanimously affirmed, without costs.
We agree with the trial court that “total cost” method of calculating construction delay damages (see, Fehlhaber Corp. & Horn Constr. Co. v State of New York, 69 AD2d 362, 368) was inapplicable under the particular circumstances of this case, and that plaintiff did not otherwise sufficiently prove