City of New York v. Cotroneo & Marino's United Electric Co.
Cases that cite this one
2 later published cases cite this decision.
- Global Crossing Bandwidth, Inc. v. Locus Telecommunication, Inc. (District Court, W.D. New York 2009)
- Welwart v. Dataware Electronics Corp. (Appellate Division of the Supreme Court of New York 2000)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
—Order, Supreme Court, New York County (Barbara Kapnick, J.), entered July 28, 1998,
The subject construction contract provided that all work was to be completed by February 26, 1991, failing which the contractor would owe the City $100 in liquidated damages for each day the project ran beyond that day. It is undisputed that the work was not completed until January 8, 1992. The City’s action to recover these liquidated damages was properly dismissed on the ground that the six-year Statute of Limitations began to run, as the contractor urges, on February 27, 1991, at which time the City had a cause of action for $100, and not, as the City urges, from January 8, 1992, when the work was completed. It is well settled that a cause of action for a breach of contract occurs at the time of the breach though no damage, other than nominal, occurs until later (Ely-Cruikshank v Bank of Montreal, 81 NY2d 399). Cases against contractors fixing accrual upon completion of the work (e.g., City School Dist. v Stubbins & Assocs., 85 NY2d 535) are distinguishable in that they involved claims for defective construction.
While the City’s action for liquidated delay damages was properly dismissed as time-barred, it was error, in the contractor’s action against the City, to preclude the City from asserting such damages as a setoff against any payments that would otherwise be due the contractor had there been no delay, and to grant the contractor summary judgment in that action. A claim that is time-barred or otherwise precluded may constitute a defense not subject to the bar that precludes assertion of the claim affirmatively (see, e.g., Northfield Eng’g v Felix Indus., 77 NY2d 332). Here, the City’s defense is that the delay was a breach of contract. There being an issue of fact as to whether the delay was caused by the contractor, the note of issue should have been stricken for disclosure on that and any