Philadelphia Corp. v. Niagara Mohawk Power Corp.
Opinion of the Court
Appeal from a judgment of the Supreme Court (Viscardi, J.), entered December 14, 1999 in Warren County, upon a decision of the court in favor of plaintiffs.
The facts of this case are set forth in our previous decision (207 AD2d 176) and are stated herein as relevant to this appeal. Plaintiff Victory Mills Hydro Company, Inc. (hereinafter plaintiff) is the owner of a hydroelectric generating facility. Defendant, a public utility, is required by contract to buy plaintiff’s entire output of electricity in accordance with the requirements of the Federal Public Utility Regulatory Policies Act of 1978 (16 USC § 824a-3) and Public Service Law § 66-c. Plaintiff’s plant is a “run of the river” facility which cannot reservoir water and generates electricity based on the natural and variable flow of water from season to season. According to plaintiffs output contract, signed in 1986,
The current dispute arose in 1992 after defendant notified plaintiff and various other hydroelectric plants
Thereafter, following a nonjury trial, Supreme Court, inter alia, determined that the New York State Dam plant, a facility operated by plaintiff NYSD Limited Partnership, had substantially increased capacity beyond contract estimates and required defendant to pay the contract rate for only a fraction of that plant’s total output. With respect to plaintiff’s generating facility, however, the court did not “find from the proof in this record that the output has been unreasonably disproportionate to the reasonable expectations of the parties as quantified by the estimate in [plaintiffs] contract.” Thus, the court concluded that plaintiff was entitled to payment for the entire output of the hydroelectric plant at the full contract price. Defendant appeals.
We affirm. Contrary to defendant’s argument, Supreme Court’s judgment herein does not violate this Court’s prior de
The record demonstrates that, in rendering its decision as to plaintiff, Supreme Court appropriately focused on the issues identified in this Court’s 1995 decision, namely, a determination as to how much of a facility’s overgeneration is entitled to the full contract rate from defendant, in light of the applicable standards of commercial reasonableness and good faith {see, UCC 2-306 [1]). With respect to plaintiffs facility, although Supreme Court found that plaintiff increased the nameplate capacity of the plant by 38% from 1.2 mW to 1.656 mW, it also concluded: “In view of the wide variation due to hydrologic conditions and the fact that in the early years the average production [of] the plant is only 14% over the contract amount, this court without site specific data is unable to conclude that the plant was modified such that its output would be beyond the normal range commercially consistent with good faith and fair dealing. In short, there is no showing that the plant has generated greater electrical output due solely to its increased name plate capacity over the capacity stated in the contract. Absent a showing that the output over a short period of time (e.g., one hour, one day) exceeded the capacity in the contract any increase may be due to river conditions and their persistence, not an increase in capacity.”
Although this Court has a “broad scope of review in a non-jury trial, we accord great deference to the credibility determinations rendered by the trial court due to its ability to view the
While defendant challenges both the methodology and conclusions reached by Cunningham, neither of defendant’s expert witnesses similarly calculated the normal variance in generation of each plant, a factor we found to be significant (207 AD2d 176, 179, supra). Notably, the documentary evidence demonstrates that, except for the anomalous 1990 output, plaintiff has consistently produced within 1,000 mWh of the contract estimate, safely within the normal expected variation calculated by Cunningham. Thus, separate and apart from the issue of whether the increase in plaintiffs nameplate capacity was in good faith, Supreme Court properly concluded, upon the record herein, that plaintiffs past overgeneration was within commercially reasonable limits and any excess output by plaintiffs plant was consistent with standard hydrological variation as opposed to the change in turbines.
Turning to the remaining argument, defendant maintains that by installing one large turbine with a 1.656 mW capacity rather than three smaller turbines with a 1.2 mW capacity as set forth in the contract, plaintiff has operated in bad faith and is not entitled to the full contract rate on its excess production. It is true that the issue of a plant’s nameplate capacity is a material issue subject to standards of commercial reasonableness. We also agree that the postcontract change in capacity at plaintiffs plant gives good cause to closely examine this issue (see, Matter of Indeck-Yerkes Energy Servs. v Public Serv. Commn., 164 AD2d 618; see also, Fulton Cogeneration Assocs.
Mercure, Crew III, Spain and Múgglin, JJ., concur. Ordered that the judgment is affirmed, with costs.
. This output contract was actually entered into between defendant and SNC Hydro, Inc., plaintiff’s predecessor in interest.
. Between January 1, 1986 and December 31, 2000, defendant was to purchase plaintiffs output pursuant to a fixed, annually escalating price schedule per kilowatt hour. From January 1, 2001 to December 31, 2025, defendant was to pay the greater of either any statutory minimum rate or its actual cost avoided as determined by the Service Classification rate number six or SC-6, which reflects the Public Service Commission’s calculation of avoided short-term power purchases by a utility.
. The latter figure is the plant’s “nameplate capacity” and reflects the theoretical maximum amount of energy that can be produced by the plant in one hour.
. This lawsuit originally involved 20 output contracts (207 AD2d 176, supra), however, plaintiff’s contract is the only remaining agreement in dispute.
. While it is true, as pointed out by defendant, that certain of the testimony offered by the generating facilities concerned their understanding of the contract terms, including the negotiation thereof, and, therefore, violated the parol evidence rule (see, Finch, Pruyn & Co. v Wilson Control Servs., 239 AD2d 814, 817), since this Court previously ruled that the contracts were unambiguous (207 AD2d 176, 178, supra), we do not find that Supreme Court improperly relied on this evidence in rendering its final judgment.
Case-law data current through December 31, 2025. Source: CourtListener bulk data.