Dick v. Doral Greens Ltd. Partnership
Opinion of the Court
Order, Supreme Court, New York County (Lorraine Miller, J.), entered on or about December 6, 2000, which consolidated and denied, as moot, the respective motions of
Plaintiffs purchased a residential unit in the Doral Greens condominium in Rye Brook, New York on July 7, 1993. As alleged in their summons with notice, dated July 2, 1999, by which plaintiffs commenced this action, the various Doral defendants were involved in the sponsorship, design, construction and sale of the Doral Greens condominium development while the other defendants were involved in its design or construction as contractors, subcontractors, engineers or architects. The notice alleges “breach of contract, breach of warranty [both express and implied], fraud, fraudulent inducement, conspiracy to defraud, negligence, negligent design [and construction] and professional malpractice in connection with the design, construction and sale of [the subject condominium unit] causing property damage and severe personal injuries and loss of services.” No complaint accompanied the summons. Separate notices of appearance with demands for service of a complaint were filed and stipulations extending plaintiffs’ time to serve a complaint entered into, the most generous of which extended plaintiffs’ time to May 31, 2000. No such stipulation was entered into as far as the Lynch defendants or RKA were concerned. The four sets of defendants separately moved, pur
In opposition to the four dismissal motions and in support of their cross motions for an extension of time to serve a complaint, plaintiffs submitted an affidavit from their attorney, who, asserting personal knowledge of the facts, argued essentially that the delay was attributable to the complexity of the litigation and the fact that he had not been retained until after the filing and service of the summons. A section of the Doral Greens condominium offering plan, identifying the roles played by the various Doral defendants in the condominium development, and Lynch Engineering, P. C., as the sponsor’s mechanical engineer, was appended, as was a copy of a subrogation complaint in an unrelated action against parties other than any of the defendants herein. The sole fact alleged in that complaint relative to this action is that a roof leak occurred in plaintiffs’ unit on May 29, 1998, some five years after they had purchased it. This leak was allegedly caused by parties other than defendants herein. Plaintiffs’ counsel asserted that he had “determined that several of the causes of action enumerated in the summons were viable and [he] could proceed with litigation that was meritorious, not frivolous and not sanctionable under the Rules of The Chief Judge.”
As is obvious from the affidavit of plaintiffs’ counsel, plaintiffs have failed to make the requisite showing of “evidentiary facts sufficient to establish a prima facie case.” (Kel Mgt. Corp. v Rogers & Wells, 64 NY2d 904, 905; Chmielnik v Rosenberg, 269 AD2d 555.) Their attorney’s reply affidavit is no more enlightening and fares no better in meeting the requisite showing of evidentiary facts. (See, Marion v Notre Dame Academy High School, 133 AD2d 614.) Although there is a conclusory allegation of construction defects in the attorney’s reply affidavit, none are identified and no facts are stated.
In light of the lack of merit and insufficiency of the facts alleged to establish a viable cause of action, the cross motions seeking an extension of time to serve the complaint should have been denied. Concur — Sullivan, P. J., Nardelli, Ellerin, Rubin and Friedman, JJ.