Ules v. City of Utica
Opinion of the Court
—Appeal from an order of Supreme Court, Oneida County (Grow, J.), entered August 5, 2002, which granted defendant’s motion to dismiss the action as untimely commenced.
It is hereby ordered that the order so appealed from be and the same hereby is unanimously affirmed without costs.
Memorandum: Plaintiffs originally commenced this action against multiple defendants, but by their amended complaint now seek damages from only the City of Utica (City). Plaintiffs allege that the City failed to make and retain certain records of complaints and investigations concerning alleged building code violations at an apartment complex in which plaintiffs formerly resided, and that the City later failed to turn over such records pursuant to plaintiffs’ requests under the Freedom of Information Law ([FOIL] Public Officers Law art 6). A FOIL request was first made by plaintiffs in March-April 2000 and almost immediately denied by City officials based on their certification that such records did not exist. Plaintiffs reiterated their FOIL requests in July and in September 2000, with the same result.
Although Supreme Court erred in deeming this action a CPLR article 78 proceeding governed by the four-month statute of limitations (see CPLR 217 [1]), the court nevertheless properly dismissed the action as untimely commenced. Plaintiffs’ action is a plenary one seeking damages for the City’s alleged denial of plaintiffs’ civil rights or for some other unspecified tortious conduct or “wrongful act” by the City (General Municipal Law § 50-i [1]). The action is therefore governed by section 50-i (1) (see generally Ruggiero v Phillips, 292 AD2d 41,
Case-law data current through December 31, 2025. Source: CourtListener bulk data.