Cunningham v. Horning Construction
Cases that cite this one
3 later published cases cite this decision.
- O'BRIEN & GERE, INC., OF NORTH AMER v. G.M. MCCROSSIN, INC. (Appellate Division of the Supreme Court of New York 2017)
- O'Brien & Gere, Inc. of North America v. G.M. McCrossin, Inc. (Appellate Division of the Supreme Court of New York 2017)
- O'Brien & Gere, Inc. of North America v. G.M. McCrossin, Inc. (Appellate Division of the Supreme Court of New York 2017)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Appeal from that part of an order of Supreme Court, Monroe County (Fraise, J.), entered February 4, 2003, that granted the motion of defendant A.A.C. Contracting, Inc. seeking a permanent stay of arbitration.
Memorandum: Supreme Court properly granted the motion of defendant A.A.C. Contracting, Inc. (AAC) seeking a permanent stay of arbitration. As the court properly determined, defendant Horning Construction (Horning) waived its right to arbitrate its claim against AAC by asserting a cross claim against AAC in which it sought recoupment of the same funds sought in its demand for arbitration (see generally De Sapio v Kohlmeyer, 35 NY2d 402, 405 [1974]). Moreover, the demand for arbitration was not made until two years after the interposition of the cross claim. Where, as here, the “participation [of Horning] in the lawsuit manifests an affirmative acceptance’ of the judicial forum, with whatever advantages [the judicial forum] may offer in the particular case, [its] actions are then inconsistent with [its] later claim that only the arbitral forum is satisfactory” (id.). Present — Green, J.P., Hurlbutt, Gorski, Lawton and Hayes, JJ.