Brite-N-Up, Inc. v. Reno
Cases that cite this one
10 later published cases cite this decision.
- Rusin v. Design-Apart USA, Ltd. (Appellate Division of the Supreme Court of New York 2019)
- Wildenstein v. 5H&CO, Inc. (Appellate Division of the Supreme Court of New York 2012)
- Wildenstein v. 5H&CO, Inc. (Appellate Division of the Supreme Court of New York 2012)
- Vanguard Construction & Development Co. v. Polsky (New York Supreme Court 2009)
- Enko Construction Corp. v. Aronshtein (Appellate Division of the Supreme Court of New York 2011)
- Design Supply Marble & Granite, Inc. v. Mills (Appellate Terms of the Supreme Court of New York 2011)
- O'Malley v. Campione (Appellate Division of the Supreme Court of New York 2010)
- Flax v. Hommel (Appellate Division of the Supreme Court of New York 2007)
- Intrepid Electrical Contracting Co. v. Serure (Appellate Division of the Supreme Court of New York 2006)
- San Sung Korean Methodist Church v. Professional USA Construction Corp. (Appellate Division of the Supreme Court of New York 2005)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
In an action, inter alia, to recover in quantum meruit for the value of work, labor, services, and materials, and based upon an account stated, the plaintiff appeals from so much of an order of the Supreme Court, Queens County (Thomas, J.), dated May 5, 2003, as granted the defendant’s motion for summary judgment dismissing the complaint and denied those branches of its cross motion which were for summary judgment dismissing the defendant’s first counterclaim to recover damages for breach of contract and to strike the affirmative defenses interposed in the defendant’s answer.
Ordered that the order is modified, on the law, by deleting the provision thereof denying that branch of the cross motion which was to dismiss the first counterclaim and substituting therefor a provision granting that branch of the cross motion; as so modified, the order is affirmed insofar as appealed from, without costs or disbursements.
The defendant established her entitlement to judgment as a
However, the defendant’s first counterclaim to recover “the difference between the contract price and the actual cost to complete the job” must be dismissed. In these circumstances the contract is rescinded and generally “[t]he parties . . . should be left as they are” (Segrete v Zimmerman, 67 AD2d 999, 1000 [1979]; see Goldstein v Gerbano, 158 AD2d 671 [1990]; Allen v Miller, 1 Misc 2d 102 [1955]). Although a homeowner may seek restitution for payments actually made for work which was not performed or for defective work (see Goldstein v Gerbano, supra; Allen v Miller, supra), the defendant’s conclusory assertions were insufficient to raise a triable issue of fact as to whether she was entitled to restitution.
The plaintiffs remaining contentions are without merit. Ritter, J.P., Smith, H. Miller and Goldstein, JJ., concur.