153 Hudson Development, LLC v. DiNunno
Cases that cite this one
7 later published cases cite this decision.
- JDS Dev. LLC v. Parkside Constr. Bldrs. Corp. (Appellate Division of the Supreme Court of New York 2024)
- Travelers Casualty & Surety Co. v. Dormitory Authority-State (District Court, S.D. New York 2010)
- Granger Construction Company, Inc. v. TJ, LLC (Appellate Division of the Supreme Court of New York 2015)
- Archstone v. Tocci Building Corp. of New Jersey, Inc. (Appellate Division of the Supreme Court of New York 2014)
- 150 Nassau Associates, LLC v. Liberty Mutual Insurance (Appellate Division of the Supreme Court of New York 2007)
- National Fuel Gas Distribution Corp. v. Hartford Fire Insurance (Appellate Division of the Supreme Court of New York 2006)
- Northeast Construction Group, Inc. v. Deconstruction, Inc. (Appellate Division of the Supreme Court of New York 2005)
This list shows which later cases cite this one. It does not say how they treated it, and no review of that has been done. Not a substitute for Shepard’s or KeyCite — verify before relying.
Opinion of the Court
Judgments, Supreme Court, New York County (Richard B. Lowe, III, J.), entered June 24 and December 19, 2003, which dismissed the complaint as against defendants Reliance Insurance and Thomsen Construction, unanimously affirmed, with costs. Appeals from orders, same court and Justice, entered May 20 and on or about November 7, 2003, which granted those
Plaintiffs failure to comply with the notice provisions of the performance bond issued by Reliance precludes it from now maintaining this action for damages against the bond’s surety. Contrary to plaintiffs contention that these notice provisions are not conditions precedent to recovery against the surety, this bond mandates that predefault notification be given to the contractor and surety by the owner (see Walter Concrete Constr. Corp. v Lederle Labs., 99 NY2d 603, 605 [2003]). Furthermore, plaintiffs failure to invoke the claim resolution mechanism in its construction contract with Thomsen bars it from seeking recovery from this entity (see Garofalo Elec. Co. v New York Univ., 270 AD2d 76, 80 [2000], lv dismissed 95 NY2d 825 [2000]).
We have considered plaintiffs other arguments and find them unavailing. Concur—Buckley, P.J., Lerner, Friedman, Marlow and Sweeny, JJ.