General Motors Acceptance Corp. v. Vucich
Opinion of the Court
OPINION OF THE COURT
In 1999, John Vucich entered into retail installment contracts for the purchase of two vehicles. Upon his default, General Motors Acceptance Corporation (hereinafter GMAC), to which these contracts were assigned, hired Tri-City Auto Recovery, Inc. to repossess them. During the repossession, Paul A. Vosteen, an employee of Tri-City, became involved in a physical altercation with Vucich.
Three separate lawsuits ensued. In the first two actions, GMAC sought payment from Vucich pursuant to the installment contracts. Vucich filed counterclaims and asserted numerous affirmative defenses, which, as here relevant, did not include claims for negligence, battery or a violation of UCC former 9-503 (L 1962, ch 553).
Supreme Court granted summary judgment in favor of GMAC on the contract claims and found that while Vucich’s personal injury claims against Tri-City and Vosteen in the third action were barred by the one-year statute of limitations applicable to battery
The sole issue presented is whether Vucich’s cause of action against GMAC was based upon a liability created by UCC former 9-503, thus warranting the application of the three-year statute of limitations period of CPLR 214 (2).
Giving the pleadings a liberal construction, as we must, we find Vucich to have sufficiently pleaded a valid cause of action for breach of the peace under UCC former 9-503. That provision sets forth a secured party’s right to repossession of collateral, without judicial process after default, if the repossession can be accomplished peaceably. Upon its violation, the debtor will have “a right to recover from the secured party any loss caused by a failure to comply with the provisions of [UCC former 9-503]” (UCC former 9-507 [1]). CPLR 214 (2) prescribes a three-year statute of limitations period for an action to recover upon a liability created or imposed by statute.
The Court of Appeals has cautioned that CPLR 214 (2) will “not automatically apply to all causes of action in which a statutory remedy is sought, but only where liability ‘would not exist
Since an employer of an independent contractor is not generally liable for an injury caused to a third party by the acts or omissions of an independent contractor or its employees (see Lazo v Mak’s Trading Co., 84 NY2d 896, 897 [1994]; Mauro v General Motors Acceptance Corp., 164 Misc 2d 871, 873 [1995]), and we find UCC former 9-503 to impose a nondelegable duty on GMAC as a secured creditor to keep the peace in the course of a repossession (see Mauro v General Motors Acceptance Corp., supra at 875),
Crew III, J.E, Carpinello, Rose and Kane, JJ., concur.
Ordered that the order is affirmed, without costs.
. The two applicable repossession provisions existing at the time of accrual were UCC 9-503 and 9-507.
. Vucich mistakenly referenced violations of the current repossession statutes which were not added to the UCC until after his action was commenced (see L 2001, ch 84, § 36).
. Despite Vucich’s classification of the cause of action as one for negligence, we agree that its substance warranted Supreme Court to designate it as one for assault and battery (see Rutzinger v Lewis, 302 AD2d 653, 654 [2003]; Locke v North Gateway Rest, 233 AD2d 578, 579-580 [1996]).
. Vucich originally challenged Supreme Court’s order granting GMAC summary judgment in action Nos. 1 and 2 and granting summary judgment to Tri-City and Vosteen in action No. 3. However, these claims were abandoned on appeal (see Matter of Lue-Shing v Travis, 12 AD3d 802, 803 n [2004]; Chase Automotive Fin. Corp. v Allstate Ins. Co., 280 AD2d 761, 763 [2001]).
. (Accord Thrash v Credit Acceptance Corp., 821 So 2d 968, 972 [Ala 2001]; Sammons v Broward Bank, 599 So 2d 1018, 1019-1020 [Fla 1992]; Fulton v Anchor Sav. Bank, FSB, 215 Ga App 456, 462-463, 452 SE2d 208, 214 [1994]; Nichols v Metropolitan Bank, 435 NW2d 637, 640 [Minn 1989]; DeMary v Rieker, 302 NJ Super 208, 220, 695 A2d 294, 300-301 [1997].)
Case-law data current through December 31, 2025. Source: CourtListener bulk data.