Defreestville Area Neighborhood Ass'n v. Planning Board
Opinion of the Court
(1) Cross appeals from a judgment of the Supreme Court (Cannizzaro, J.), entered October 28, 2003 in Rensselaer County, which, inter alia, in a proceeding pursuant to CPLR article 78, granted respondents’ motions to partially dismiss the petition, (2) appeal from an order of said court (Cannizzaro, J.), entered March 9, 2004 in Rensselaer County, which,
The history of this case begins with an October 2002 application to respondent Town Board of the Town of North Greenbush by respondent Oak Hill Apartments, LLC for the construction of a luxury apartment complex on 20.62 acres of land in the Town of North Greenbush, Rensselaer County. This property is also located within the unincorporated hamlet of Defreestville. Ultimately, respondent Planning Board of the Town of North Greenbush, in compliance with the State Environmental Quality Review Act (hereinafter SEQRA) (see ECL art 8), issued a conditioned negative declaration (hereinafter CND) for the project and respondent Zoning Board of Appeals of the Town of North Greenbush approved a request for an area variance, thus prompting this litigation.
Petitioners are individuals who live in close proximity to the proposed complex, as well as a not-for-profit corporation comprised of approximately 250 Defreestville residents. We begin by acknowledging that petitioners have legitimate concerns about this project specifically, as well as the future growth and development of their hamlet generally, which are deserving of their personal and collaborative efforts. In the end, however, upon this Court’s review of the voluminous records in these two consolidated appeals—totaling in excess of 5,000 pages—we are compelled to conclude that Supreme Court (Canfield, J.) erred in granting the petition to annul the actions taken by the Planning Board and Zoning Board.
There are three prefatory matters which require discussion, namely, mootness, standing and allegations that the Town Board erred in excluding the subject property from the scope of a draft generic environmental impact statement (hereinafter GEIS) being prepared for potential rezoning of an area referred to as the Routes 4 and 43 corridor. First, since petitioners did not delay in commencing this proceeding and requested injunctive relief on more than one occasion to preserve the status quo, albeit unsuccessfully, this proceeding is not moot despite the apparent
Additionally, we are satisfied that petitioners have standing, both as individuals and as a neighborhood association, to challenge the various determinations of the Planning Board and Zoning Board concerning this project.
Next, we are unable to conclude that Supreme Court (Cannizzaro, J.) erred in granting a preanswer motion to dismiss the second cause of action, premised on the Town Board’s alleged failure to include the subject property within the scope of the GEIS. As of the commencement of this proceeding, the Town Board had not yet rendered a final determination on that ancillary matter and thus the second cause of action was properly dismissed.
We turn now to the issue of whether the Planning Board
In January 2003, the application was amended to seek approval for 252 units as zoned; that is, the Planned Development District request was withdrawn. At this time, Oak Hill submitted an application for site plan approval and evaluation in accordance with SEQRA to the Planning Board and also applied for an area variance to the Zoning Board concerning the project’s density. As now amended, the project resulted in a density of 12.22 units per acre, well over the 4.36 units per acre permitted under the local ordinance. In early February 2003, the Planning Board designated itself as lead agency, thus assuming the responsibility for determining whether an environmental impact statement was required in connection with the project (see 6 NYCRR 617.2 [u]). In this capacity, the Planning Board consulted and solicited comments from approximately 20 agencies and conducted a coordinated SEQRA review with eight agencies. Resulting agency comments included concerns about storm water discharge, the potential presence of rare species on the site and the need for an archaeological survey.
A joint hearing was conducted on February 24, 2003 by the Planning Board and Zoning Board and yet another Planning Board meeting was conducted on March 3, 2003. Public comments were heard at both meetings and written comments were also received by the Planning Board concerning various aspects of the project. Indeed, between February 21, 2003 and March 12, 2003 over 25 letters or e-mails were submitted to the Planning Board from residents, as well as a handful of nonresidents, concerning the project. At each step of the process, Oak Hill responded to all oral and written comments and concerns.
Within a few days of the March 3, 2003 meeting, at which density and increased traffic continued to be the primary concerns of the public, Oak Hill agreed to reduce the proposal
This extensive record reveals that the Planning Board, with the guidance and assistance of its own independent engineering firm and legal counsel, complied with the procedural and substantive requirements of SEQRA both in determining that the project would have no significant environmental impact and in issuing the CND. In reviewing its determination to issue a CND, this Court’s review is strictly limited to “whether the [Planning Board] identified the relevant areas of environmental concern, took a ‘hard look’ at them, and made a ‘reasoned elaboration’ of the basis for its determination” (Matter of Jackson v New York State Urban Dev. Corp., 67 NY2d 400, 417 [1986]; see Matter of New York City Coalition to End Lead Poisoning v Vallone, 100 NY2d 337, 348 [2003]). “While judicial review must be meaningful, the courts may not substitute their judgment for that of the agency for it is not their role to ‘weigh the desirability of any action or [to] choose among alternatives’ ” (Akpan v Koch, 75 NY2d 561, 570 [1990], quoting Matter of Jackson v New York State Urban Dev. Corp., supra at 416; accord Matter of Merson v McNally, 90 NY2d 742, 752 [1997]).
In fact, numerous detailed documents were presented to the Planning Board on the project, including original and revised site plans, a comprehensive traffic impact report, as well as a supplemental traffic impact report, a wetland delineation report, original and revised long environmental assessment forms, applications for an area variance, original and amended project narratives, detailed engineering reports, an archaeological assessment, a geotechnical study, a housing market study, excerpts from a fiscal impact analysis guidebook concerning projections of school population attributable to new development and multiple written responses by Oak Hill to agency and public concerns that arose. Although many areas of environmental concern were identified and addressed by the Planning Board, such as wetlands, archaeological resources and rare species, the predominate concerns raised throughout the process were traffic and the impact the project would have on the growth and character of the neighborhood, particularly given its density.
With respect to traffic, a traffic study prepared on November 21, 2002, at a time when the project design consisted of 272 units, concluded that there is adequate capacity in the surrounding infrastructure to absorb all traffic generated by the project without degrading existing levels of service. While this study was called into question by petitioners, each comment or concern was duly responded to by Oak Hill. Moreover, this traffic impact study was never actually refuted with competent proof. More importantly, the Department of Transportation indicated in late January 2003 that it had reviewed the study and agreed that no offsite action was necessary to mitigate the impact of the traffic generated by the project.
With respect to the growth and character of the neighborhood, the record confirms the Planning Board’s findings that the project is situate within a zone that permits multifamily housing, as well as other more intense uses such as office space. Moreover, with the exception of density, the project complied with all other requirements for site plan approval. As to density,
Similarly, our review of the record discloses no bias or predetermination on the part of the Planning Board against performing an environmental impact statement.
We turn next to the Zoning Board’s decision to grant an area variance. As recently reiterated by the Court of Appeals, “local
The Zoning Board, again with the assistance of independent consultants, adhered to the statutory criterion outlined under Town Law § 267-b, which required it to engage in a balancing test, weighing the benefit to Oak Hill against “the detriment to the health, safety and welfare of the neighborhood or community” (Town Law § 267-b [3] [b]) and “made a well-reasoned decision based on a full consideration of the evidence before it and its members personal familiarity with the project site and surrounding areas” (Matter of Oates v Village of Watkins Glen, 290 AD2d 758, 762 [2002]). At a May 14, 2003 public hearing, traffic and density were again primary concerns and these issues were fully discussed by the Zoning Board members at that time and reflected in the Zoning Board’s detailed written decision.
The Zoning Board further noted that the average population density of similar apartment complexes in the Capital District is
To the extent not otherwise discussed, all other issues have been reviewed and rejected as being without merit.
Mercure, J.P., Crew III, Spain and Kane, JJ., concur. Ordered that the judgment entered October 28, 2003 is affirmed, without costs. Ordered that the appeal from the order entered March 9, 2004 is dismissed, without costs. Ordered that the judgment entered April 23, 2004 is reversed, on the law and the facts, without costs, and petition dismissed.
. Motions for a preliminary injunction preventing construction of the project were twice requested by petitioners and twice denied by Supreme Court (Cannizzaro, J.) before this matter was transferred to Supreme Court (Canfield, J.). Within 10 days of this transfer, the petition was granted.
. Standing was denied to one individual petitioner (Brian Dwyer) and no petitioner or Dwyer takes issue with this decision on appeal. Accordingly, any issue regarding Dwyer’s standing is deemed abandoned (see Matter of Center Sq. Assn. v City of Albany Bd. of Zoning Appeals, 9 AD3d 651 n [2004]).
. Petitioners separately appealed from the order denying their motion to amend. As an appeal as of right does not lie from a nonfmal order in a CPLR article 78 proceeding, the appeal from this order must be dismissed (see CPLR 5701 [b] [1]; Matter of Baker v Town of Roxbury, 220 AD2d 961, 962-963 [1995], lv denied 87 NY2d 807 [1996]). However, the appeal from the final judgment brings up for review the propriety of this order (see Matter of Baker v Town of Roxbury, supra).
. Notably, petitioners never attempted to resurrect this cause of action by thereafter seeking to amend the petition to include these allegations after the GEIS was finally adopted. They have, however, allegedly commenced a separate CPLR article 78 proceeding challenging the GEIS.
. While there is a separate argument that the Planning Board erred in declining requests to table the subject project pending completion of the GEIS, which would survive dismissal of the second cause of action, it is, in any event, unpersuasive. A review of the time line of events reveals that consideration of the instant project was well under way and nearing its final stages before the Town Board began preparation of the GEIS or issued a draft scope for it. Given this timeline, and because the subject project did not implicate rezoning concerns, we find no abuse of discretion in the Planning Board’s decision to continue to proceed with its review of the project despite the Town Board’s commitment to perform the GEIS.
. Indeed, a phased archaeological investigation was conducted on the site and reports were issued to the Planning Board.
. While the project as originally submitted constituted a type I action under SEQRA as it involved more than 250 apartment units in a town with a population less than 150,000 (see 6 NYCRR 617.4 [b] [5] [iii]), its final scaled down version was appropriately determined to constitute an unlisted action (see id.; see also 6 NYCRR 617.2 [ak]).
. Notably, one Planning Board member stated at the March 27, 2003 special meeting on the project that “[t]his is not going to be an easy decision for anyone sitting here tonight. And that’s based on community character because we’re all part of this community.”
. To the extent that Supreme Court found the Town’s alleged bias to be supported by “the inexplicable decision to carve this large parcel of commercial property out of the properties that would be studied as part of the GEIS,” we again note that the precise issue of the scope of the GEIS was no longer extant at that point in the litigation and thus it was not a proper indicator of bias.
. The rationale behind limiting judicial review in these matters, namely, that zoning decisions should be made by representatives from the local community who typically possess familiarity with local conditions necessary to make sensitive planning decisions (see Matter of Cowan v Kern, 41 NY2d 591, 599 [1977]), is particularly apt in this case.
. Notably, one Zoning Board member stated on the record that “[m]y decision is going to be very hard. One of the hardest I’ve made—since 1985.”
. Under the express terms of the statute, a self created difficulty “shall not necessarily preclude the granting of the area variance” (Town Law § 267-b [3] [b]).